Question to the Ministry of Defence:
To ask the Secretary of State for Defence, what the average procurement cycle time to delivery was in the latest period for which data is available.
The Defence Industrial Strategy set out average times to contract for major projects (such as tanks, frigates and aircraft) of six years, and for pace-setting modular upgrades (such as comms, sensors and weapons upgrades) of three years. We have set targets to reduce these averages to two years and one year respectively, and a target of three-month cycles for rapid commercial exploitation.
The introduction of this segmented approach to procurement, with associated timescale targets, is a key element of our acquisition system reforms. This initiative, and our move to a portfolio-driven approach, will drive greater to increase pace and agility in delivery. Our support to Ukraine has shown the pace at which we can deliver.