Trident Submarines: Procurement

(asked on 10th October 2025) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, with reference to page 42 of the National Security Strategy 2025, published in June 2025, CP 1338, how much of the £10 billion contingency for the Dreadnought programme he estimates will be spent this Parliament.


Answered by
Luke Pollard Portrait
Luke Pollard
Minister of State (Ministry of Defence)
This question was answered on 18th October 2025

To date £3.37 billion contingency has been utilised with the remainder allocated to future years including beyond the current Parliament. Dreadnought contingency spend is reported to Parliament via the Defence Nuclear Enterprise Annual Update, once final outturn figures are confirmed.