Question to the Department for Transport:
To ask the Secretary of State for Transport, with reference to the oral contribution of the Secretary of State for Transport of 8 July 2025 on Road and Rail Projects, Official Report, columns 822-3, whether it is her policy that the full cost of the midlands rail hub should be paid for by her Department; and when she expects the midlands rail hub to be completed.
A sum of £123m has been allocated by the Government to deliver detailed designs of the first phase of MRH. The designs will produce a more accurate cost estimate, a delivery schedule and subsequently form the basis of a ‘Final Investment Decision’. This phase is due to enter service in the early 2030s. The costs and delivery timescales for later phases are subject to further development work and subsequent investment decisions.