A27

(asked on 9th March 2017) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, how much has been budgeted for upgrades to stretches of the A27 at (a) Arundel, (b) Worthing/Lancing and (c) Lewes/Polegate.


Answered by
John Hayes Portrait
John Hayes
This question was answered on 14th March 2017

In line with Highways England’s commitment to commence upgrades to sections of the A27 between 2015-2020, they are currently developing options for schemes at Arundel, Worthing / Lancing and Lewes / Polegate. As stated in the Road Investment Strategy and subject to achieving value for money the funding for these projects will be within the following ranges:

A27 Arundel Bypass: £100m - £250m

A27 Worthing to Lancing: £50m - £100m

A27 East of Lewes: £50m - £100m

Reticulating Splines