Question to the Department for Transport:
To ask the Secretary of State for Transport, what her planned timetable is for funding remedial work on the Orwell Bridge, Suffolk; and if she will take steps to accelerate the provision of that funding.
The replacement of all 4 bridge joints on Orwell Bridge had been included within a scheme of planned works scheduled for construction starting in 2027. Due to the recent failure of one of the two westbound joints, National Highways is accelerating the replacement of both joints on the westbound carriageway to start within the current financial year. National Highways is in the process of developing the proposal for replacing the 2 eastbound joints as part of the planned scheme of works.