Railways: Midlands

(asked on 11th June 2025) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, with reference to the oral contribution of the Chancellor of the Exchequer at the Spending Review 2025 on 11 June 2025, what funding will be provided to progress the next stage of the Midlands Rail Hub.


Answered by
Simon Lightwood Portrait
Simon Lightwood
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 17th June 2025

The Chancellor’s commitment to progress Midlands Rail Hub West in the 2025 Spending Review follows the release of £123 million last year to design the first phase, which could be delivered by the early 2030s.

Reticulating Splines