Question to the Department for Business, Energy and Industrial Strategy:
To ask the Secretary of State for Business, Energy and Industrial Strategy, if he will make an estimate of the (a) earliest potential start date and (b) potential peak capacity as a proportion of grid requirement of the proposed Xlinks interconnector between the UK and Morocco.
Xlinks has indicated that the project can supply 3.6 GW of capacity, approximately 8% of GB transmission demand (or approximately 6% of peak underlying – transmission and distribution – demand), from 2030. The Department has not verified the feasibility of proposed capacity of the project and project timelines.