Question to the Department for Transport:

To ask the Secretary of State for Transport, pursuant to the Answer of 20 May 2025 to Question 51962 on Abellio Greater Anglia and c2c: Standards, what her planned timeline is for the improvements to Cambridge South Station; when the Transport and Works Act Order for the project was issued; when did construction begin; and when it is expected to be completed.


Answered by
Simon Lightwood Portrait
Simon Lightwood
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 3rd June 2025

The Transport and Works Act Order for Cambridge South was granted in December 2022, and construction work began on site in February 2023. We expect the new station to open early in 2026; an exact date will be confirmed later in the year.