Retford Station: Lifts

(asked on 15th October 2019) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, when he expects work to be commenced on the lower level platform lift at Retford station.


Answered by
Nusrat Ghani Portrait
Nusrat Ghani
Minister of State (Minister for Europe)
This question was answered on 21st October 2019

All Access for All projects are due to be complete by 31 March 2024 at the latest. Retford is making good progress. The option selection process is finished and Network Rail will shortly start design works. Once that is complete we will have confirmed start and completion dates with construction scheduled to ensure minimal disruption to passengers.