Question to the Department for Energy Security & Net Zero:
To ask the Secretary of State for Energy Security and Net Zero, pursuant to the Answer of 5 September 2024 to Question 3867 on Hitachi: Wylfa Power Station, if he will provide a breakdown of how much of the £160 million total was spent on the site at (a) Wylfa and (b) Oldbury.
Great British Nuclear agreed to pay £115m for the Wylfa site and up to £45m for the Oldbury site, excluding taxes.