Question to the Ministry of Defence:
To ask the Secretary of State for Defence, with reference to his Department's Annual Report and Accounts for 2021-22, published in July 2022, HC 500, and for 2022-23, published in July 2023, HC 1468, what the (a) Consultancy and (b) Temporary Staff costs were for each contract for MOD main building in (i) 2022 and (ii) 2023.
The Department does not maintain records of temporary staff and consultancy contract numbers and expenditure by location. However, we can confirm that the value of expenditure on consultancy and temporary staff incurred by the Department’s Head Office in 2022-23 and 2021-22 was as follows:
Head Office and Enabling Organisations | 2022-23 £million | 2021-22 £million |
Consultancy | 16.066 | 10.620 |
Temporary Staff | 11.480 | 6.425 |
Head Office includes a number of different teams for example the Directorate General Finance, Chief of Defence People, Secretariat, Policy and Operations as well as others.