High Rise Flats: Construction

(asked on 31st March 2025) - View Source

Question to the Ministry of Housing, Communities and Local Government:

To ask the Secretary of State for Housing, Communities and Local Government, what estimate she has made of the number of (a) homes and (b) affordable homes that would be created in buildings awaiting Gateway Two approval from the Building Safety Regulator.


Answered by
Alex Norris Portrait
Alex Norris
Parliamentary Under-Secretary (Housing, Communities and Local Government)
This question was answered on 8th April 2025

The Building Safety Regulator (BSR) was established by the previous Government and became the Building Control Authority for higher-risk buildings in England from October 1, 2023.

As with any newly established regulator it is typical that there will be a bedding in period as it develops its operations. As the industry adjusts to the new regulatory regime a lot of poor quality and incomplete applications have been submitted. The volume of sub-standard applications demands much of BSR's time and resources which has a knock-on effect on the processing time for all applications.

The majority of the 8 applications exceeding 52 weeks are transitional applications which were transferred into the building safety regime from private sector building control companies that ceased trading with construction already underway. As they were not started under the gateway regime developers have had to gather the evidence to demonstrate compliance with Gateway Two. In the meantime the BSR has allowed these projects to continue construction whilst demonstrating compliance with building regulations. These are unique cases which have arisen as part of the transition process and are therefore atypical.

Of the applications exceeding 12 and 26 weeks, these will be subject to agreed extensions of time between the BSR and developers. These are often required because the applications have failed to fully demonstrate how the building will comply with building regulations and more information is needed. This is a core responsibility of what the BSR was set up to do and ensures that new buildings meet the requisite safety standards that are set out in law.

Some delays to the processing of applications are due to capacity and efficiency issues that exist within the BSR which the new government is seeking to address. This Government has provided an additional £2.1 million to the BSR to engage additional staff to increase capacity which, alongside several efficiency initiatives, is seeing processing times reduce.

The Department continues to work with the BSR to monitor timescales and scrutinise progress. The safety of buildings remains a top priority for the department and the BSR, and legal safety requirements must be adhered to.

The data the BSR reports to the department does not categorise between homes and affordable homes. The following figures are for new build Higher Risk Buildings (HRBs), Non-HRB conversion to HRB and Category A refurbishments (where this refurbishment increases the number of residential units by 1 or more unit). Note that the figures are nested i.e. the 18,424 includes the 10,192 and the 912; and the 10,192 includes the 912.

The number of homes which will be provided on completion by the buildings that have been waiting for Gateway 2 approval from the Building Safety Regulator for more than 52 weeks.

912 residential units (8 applications)

The number of homes which will be provided on completion by the buildings that have been waiting for Gateway 2 approval from the Building Safety Regulator for more than 26 weeks.

10,192 residential units (46 applications)

The number of homes which will be provided on completion by the buildings that have been waiting for Gateway Two approval from the Building Safety Regulator for more than 12 weeks.

18,424 residential units (85 applications)

The estimate of the number of homes that would be created in buildings awaiting Gateway Two approval from the Building Safety Regulator.

29,506 residential units (130 applications). These numbers include applications currently within the 0–12-week period.