RAF Brize Norton

(asked on 18th August 2021) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, whether the repair of the runway at RAF Brize Norton has been completed.


Answered by
Jeremy Quin Portrait
Jeremy Quin
This question was answered on 7th September 2021

Following the most recent works to the surface, repair of the runway at RAF Brize Norton has been completed and was handed to the Operating Authority on 7 August 2021. However ongoing maintenance will be required and will be scheduled to take place on a pre-agreed basis.