Question to the Ministry of Defence:
To ask the Secretary of State for Defence, whether the upgrade of 10 Dock at HMNB Devonport will be completed to its original schedule.
This Government inherited a number of programmes that were late and delayed. I have commented frequently on this in Parliament. The MOD and the National Infrastructure and Service Transformation Authority (NISTA) assurance processes have highlighted issues with the original delivery date in 2027. Positive progress has been made where10 Dock has recently moved into the construction phase with the commencement of the dockside buttresses, but challenges remain with the delivery of the Submarine Waterfront Infrastructure Future (SWIF) programme. The MOD is working closely with NISTA and the contractor to recover the programme, and we are currently reviewing opportunities to accelerate this work following the Nuclear Regulatory Review.