Question to the Department for Environment, Food and Rural Affairs:
To ask the Secretary of State for Environment, Food and Rural Affairs, where in Northern Ireland border control posts have (a) been and (b) are being constructed for the purpose of complying with the Windsor Framework.
In line with the commitments we have made under the Windsor Framework, SPS inspection facilities are under construction in Northern Ireland at the ports of Belfast, Larne, Foyle and Warrenpoint. Preparations are well underway, and they will be operationally ready by July 2025.
The Government has committed to a maximum funding envelope of £192.3 million. Of this envelope, Defra has spent £70.7 million up to the 28 February 2025, the latest data currently available.