Great Western Main Line: Electrification

(asked on 6th March 2025) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what assessment she has made of the (a) financial and (b) time impact of the deferred electrification between Bristol and Chippenham on commuters.


Answered by
Lilian Greenwood Portrait
Lilian Greenwood
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 14th March 2025

Electrification of the line between Bristol Temple Meads and Chippenham was deferred in 2016. Passengers on this line are benefiting from the bi-mode rolling stock introduced in 2019 which are delivering faster and more reliable end to end journeys. No subsequent assessment has been made since the deferral of electrification on this line.