East West Rail Line: Electrification

(asked on 12th February 2025) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what assessment she has made of the potential impact of the proposed discontinuous electrification of East West Rail on (a) capital costs and (b) operating costs of the railway.


Answered by
Simon Lightwood Portrait
Simon Lightwood
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 26th February 2025

The cost of discontinuous electrification is already included in the publicised capital cost range of the project and the option of full electrification is still under consideration. However, electrification (discontinuous or full) is expected to significantly reduce operating costs for the line over its whole life.