Question to the Ministry of Defence:
To ask the Secretary of State for Defence, what is the parent project for each of the new build projects in the Devonport Royal Dockyard site plan; and what recent estimate he has made of the cost of each parent project.
The Devonport Submarine Infrastructure Programme will involve the investment of approximately £2.5 billion to provide new and refurbished facilities at HM Naval Base Devonport. The Department expects to gain beneficial use of the facilities currently under construction in 2024 (9, 14 and 15 Docks) and 2027 (10 Dock). The estimated costs for each project are commercially sensitive but they fall within the overall estimate of £2.5 billion.