The number of maintenance callouts which have been made to HMNB Clyde is shown in the table below. This covers both Clyde sites, Faslane (including Clyde Off-site Centre) and Coulport and includes c400 buildings/facilities. By their nature defects are wide ranging and this represents everything from minor to major.

Category

Volume

A

Roofing

570

B

Call outs for heating/hot water issues

732

C

Electrical

11732

D

Pest Control

265

E

Damp and Mould

136