Medway Secure Training Centre: G4S

(asked on 14th January 2016) - View Source

Question to the Ministry of Justice:

To ask the Secretary of State for Justice, how many times G4S has been in breach of its contract at Medway STC since it was awarded that contract; for what reasons each such breach occurred; and what fines were incurred by G4S for each of these breaches.


Answered by
Andrew Selous Portrait
Andrew Selous
Second Church Estates Commissioner
This question was answered on 9th February 2016

Since the contract was awarded in 1997, there have been two instances of financial remedies on G4S’s contract at Medway STC, both for failure to comply with procedures. The financial penalties were for a total of £707.40. We are examining whether the allegations made by Panorama would constitute a breach of contract.