East West Rail Line: Construction

(asked on 7th January 2025) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what estimate her Department has made of the cost of constructing East-West Rail in 2024 prices.


Answered by
Lilian Greenwood Portrait
Lilian Greenwood
Government Whip, Lord Commissioner of HM Treasury
This question was answered on 15th January 2025

£1.3bn has been provided towards the delivery of East West Rail Connection Stage 1 (CS1) which will provide services from Oxford to Bletchley and Milton Keynes.

The capital cost estimate for Connection Stages 2 (Oxford-Bedford) and 3 (Oxford-Cambridge) is £5bn-£6bn in 2021 prices. Final costs for the project will be driven by scope and design choices.

Reticulating Splines