To ask the Secretary of State for Transport, what his most recent estimate is of the annual number of timetabled passenger train services that arrived (a) within five minutes of and (b) five minutes or more after the scheduled time due to factors attributable to the franchised train operating company in each year since 2004.


Answered by
 Portrait
Claire Perry
This question was answered on 22nd July 2014

The criteria for establishing delay causes are to be found in the Delay Attribution Guide, issued by the Delay Attribution Board – a joint rail industry body remitted to provide guidance to the industry on delay attribution issues.

The current guide was issued in April 2014. Copies of the all the guides since 2007 can be seen at:

http://www.delayattributionboard.co.uk/delayattributionguides.htm

The Department does not make estimates with regard to the attribution of delay in respect of the annual number of timetabled passenger train services that arrived, either within 5 minutes or not, of their scheduled arrival time.

The industry uses the Delay Attribution Guide to attribute delays by total minutes of delay, not by number of trains. The Office of Rail Regulation is beginning to publish such information; see

http://orr.gov.uk/__data/assets/pdf_file/0004/13792/network-rail-monitor-2013-14-q4.pdf (page11) for the 2013-14 figures as to how industry delay was apportioned for each operator and nationally.