Question to the Foreign, Commonwealth & Development Office:
To ask the Secretary of State for Foreign, Commonwealth and Development Affairs, with reference to the £785 million pledged by his Department to the United Nations Population Fund Supplies Partnership from 2020-25, what the planned schedule of payments was for that funding; and how much of that funding has been disbursed and on what dates as of 23 October 2023.
In 2019, the UK pledged £425 million to the United Nations Population Fund (UNFPA) Supplies Partnership (not £785 million)
Following the signing of its first agreement, the UK disbursed £65 million in 2020 as planned. The UK signed a second agreement in 2020 to provide the remaining £360 million from 2020-2025 but this was reduced in 2021 following reductions in ODA spending. We are currently providing £60 million a year to UNFPA Supplies Programme.
Payments can be found on DevTracker: https://devtracker.fcdo.gov.uk/projects/GB-GOV-1-300713/documents.