Armoured Fighting Vehicles: Procurement

(asked on 14th July 2026) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, what are the expected timelines of the Land Mobility Programme.


Answered by
Luke Pollard Portrait
Luke Pollard
Minister of State (Ministry of Defence)
This question was answered on 20th July 2026

The Land Mobility Programme (LMP) is a 20-year, pan-Defence programme to deliver digitally enabled, adaptable utility and protected mobility vehicles to the Joint Force. LMP comprises of three discrete sub-programmes: Heavy Protected Mobility (HPM), Light Protected Mobility (Lt PM) and Light Mobility Vehicle (LMV).

Each sub-programme is subject to separate investment approvals. Both HPM and Lt PM are in their Concept Phases, with timelines yet to be finalised. LMV is in its Assessment Phase with a competition due to start this year. Delivery of the first LMV platforms is anticipated from 2028, subject to successful competition and Departmental approvals.