Question to the Department for Environment, Food and Rural Affairs:
To ask the Secretary of State for Environment, Food and Rural Affairs, what flood (a) prevention and (b) relief measures have been put in place to support communities along the Thames between Weybridge and Long Ditton in the event of flooding in winter 2024-25.
Following Storm Henk, the Environment Agency (EA) has undertaken a significant amount of debris clearance on weir structures, including the removal of a number of sunken & stricken vessels. The cost of the clean-up operation undertaken by our teams and supply chain partners has been more than £1 million over the last 6 months.
The main flood risk reduction plan currently being developed along this area is the proposed River Thames Scheme (RTS). It is a partnership between the EA, Surrey County Council and other local partners, that will reduce the risk of flooding for communities from Staines to Teddington, including between Weybridge and Long Ditton. This will be achieved through the creation of a new flood channel, in two parts, and capacity improvements to Sunbury, Molesey and Teddington weirs on the Thames and to the river in the Desborough area. RTS will reduce flood risk to around 11,000 homes and 1,600 businesses.
The EA are also looking at how to reduce the impact of flooding in Thames Ditton. Measures under consideration include raised barriers and property flood resilience measures to reduce the impact of flooding and allow a faster recovery. Any solution must be cost beneficial to attract public funding.