High Speed 2 Railway Line

(asked on 11th February 2021) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what estimate he has made of the (a) total costs incurred to date and (b) total expenditure required for land and property acquisition in relation to Phase 1 of High Speed Two.


Answered by
Andrew Stephenson Portrait
Andrew Stephenson
Minister of State (Department of Health and Social Care)
This question was answered on 22nd February 2021

a) The costs incurred to date for land and property acquisition is £2,345 million. Within this £1,202 million is for Compulsory Purchase, £287 million for Schemes, £624 million through Private Agreement, and £232 million for Statutory Blight.

b) The final amount of compensation payable will be dependent on a number of factors including the take-up of discretionary schemes. HS2 Ltd is currently tracking to deliver its programme of acquisitions within the funding envelope agreed with the Department.