National Grid

(asked on 29th June 2026) - View Source

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what assessment he has made of the adequacy of current electricity grid capacity to meet projected demand by 2035.


Answered by
Martin McCluskey Portrait
Martin McCluskey
Parliamentary Under-Secretary of State (Department for Energy Security and Net Zero)
This question was answered on 7th July 2026

The National Energy System Operator (NESO) conducts independent modelling of future electricity demand and supply and strategic planning of the transmission network.

NESO’s Future Energy Scenarios (FES) provide a range of credible pathways for Great Britain's energy system to 2050. This informs strategic electricity network planning by assessing future demand, generation, storage and flexibility requirements.1

NESO’s Beyond 2030 Update report (published 30th June), draws on the FES, and sets out the network infrastructure needed through the 2030s.2

NESO’s assessment indicates that demand can be met through timely delivery of recommended network infrastructure to enable generation planned for the 2030s.

  1. Future Energy Scenarios (FES) | National Energy System Operator
  2. Beyond 2030 - Electricity Transmission Update | National Energy System Operator