Trident Submarines

(asked on 20th April 2018) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, what recent estimate his Department has made of the cost of the trim and compensation system for the Dreadnought programme; and whether that estimate is an increase on previously made estimates.


Answered by
Guto Bebb Portrait
Guto Bebb
This question was answered on 27th April 2018

Costs of individual systems on Dreadnought are managed within the programme's overall £31 billion budget, which is funded by Defence. I am withholding details of the cost of this system as disclosure would, or would be likely to, prejudice commercial discussions and interests.