High Rise Flats: Fire Prevention

(asked on 25th February 2026) - View Source

Question to the Ministry of Housing, Communities and Local Government:

To ask the Secretary of State for Housing, Communities and Local Government, what estimate he has made of the average waiting for the Building Safety Regulator to approve the remediation of residential flats in London.


Answered by
Samantha Dixon Portrait
Samantha Dixon
Parliamentary Under-Secretary (Housing, Communities and Local Government)
This question was answered on 4th March 2026

The monthly Building Control Approval Application dataset January 2026 showed that the average approval timeframe for remediation projects in London was 30 weeks.

We recognise that processing times need to improve, and we will be bringing forward a Building Safety Regulator remediation improvement plan in the coming weeks detailing how we intend to work with the sector to achieve improvements.