(asked on 6th February 2026) - View Source

Question to the Wales Office:

To ask the Secretary of State for Wales, if she will provide a breakdown by operations, maintenance, renewals and enhancement of funding committed by the UK Government to Welsh railways between 2025–26 and 2028–29.


Answered by
Jo Stevens Portrait
Jo Stevens
Secretary of State for Wales
This question was answered on 12th February 2026

Estimated Operations, Maintenance and Renewals (OMR) expenditure for Wales during Control Period (CP) 7 is broken down as follows:

2024-25 - £502 million

2025-26 - £447 million

2026-27 - £503 million

2027-28 - £499 million

2028-29 - £487 million

In addition to this, the UK Government has announced at least £445 million for rail enhancements in Wales, to right years of underfunding by previous Conservative Governments and unleash Wales’ economic potential.

This will mean new stations, more and faster trains on the key lines across North and South Wales, connecting people with the new, well-paid jobs we are creating across Wales.

The UK Government will set out more detail on the pipeline of projects that we will deliver very shortly.