Question to the Ministry of Justice:

To ask the Secretary of State for Justice, what estimate he has made of the number of new prisons places that will result from the building of prisons that received planning approval since 5 July 2024; what his proposed timetable is for these prison places to become available.


Answered by
Jake Richards Portrait
Jake Richards
Assistant Whip
This question was answered on 11th February 2026

As set out in the December 2024 10-Year Prison Capacity Strategy, we are committed to delivering an additional 14,000 prison places and aim to do so by 2031. Around 4,300 of these places have received planning permission since 5 July 2024. This includes full planning permission for a c.1,500 place prison near the existing HMPs Grendon and Springhill and outline planning permission for a c.1,700 place prison near the existing HMPs Garth and Wymott. We will seek to deliver these new places as quickly as possible and continue to identify opportunities to accelerate delivery of places wherever possible.

There are currently c.5,000 places under construction across the prison estate, including c.1,700 at our next new prison, HMP Welland Oaks, in Leicestershire.

Reticulating Splines