Lower Thames Crossing: Public Finance

(asked on 21st January 2026) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, whether publicly funded works on the Lower Thames Crossing will commence after a Full Business Case has been produced and approved.


Answered by
Simon Lightwood Portrait
Simon Lightwood
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 30th January 2026

Publicly funded construction enabling works have already commenced north and south of the River Thames. These include ground works to create haul roads, construction of site compounds, utility works, ecological and archaeological works and extensive pre-construction surveys are ongoing. The project continues to progress through the required assurance and governance processes and the full business case will follow ahead of private sector investment.