UK Submarine Supply Chain Debate

Full Debate: Read Full Debate
Department: Ministry of Defence

UK Submarine Supply Chain

Thomas Docherty Excerpts
Wednesday 10th July 2013

(10 years, 10 months ago)

Westminster Hall
Read Full debate Read Hansard Text Read Debate Ministerial Extracts

Westminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.

Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.

This information is provided by Parallel Parliament and does not comprise part of the offical record

Lord Walney Portrait John Woodcock
- Hansard - - - Excerpts

Indeed I can, and I thank the hon. Gentleman for his contribution. As he knows, it was the previous Labour Government who took the difficult but right decision to press ahead with Vanguard renewal. We set in place that programme, and we were disappointed that, following the coalition agreement, a delay was put on main gate and the in-service date. That has stretched the programme to its limit, but the Labour party remains committed to a minimum credible deterrent as long as other countries have it. Once one makes that call and genuinely believes it, as we do, the argument that I am setting out today is that there is only one logical conclusion, which is to renew Vanguard on the programme that is under way at the moment, or indeed even to speed it up.

Thomas Docherty Portrait Thomas Docherty (Dunfermline and West Fife) (Lab)
- Hansard - -

My apologies for being slightly held up; the Defence Committee over-ran by a couple of minutes. I had the great privilege of visiting the yard with my hon. Friend a few weeks ago. Given the experience of the Astute programme, will he share with the Chamber the consequences of introducing another delay?

--- Later in debate ---
Philip Dunne Portrait Mr Dunne
- Hansard - - - Excerpts

I am naturally grateful to the hon. Lady for reminding me. She pre-empts my own remarks. I am happy for her to endorse that, because it is not just Cumbria that contributes to this enormous effort.

From specialist diver support courtesy of Divex in Aberdeen, to marine valves courtesy of Hale Hamilton in Uxbridge, not so far away, few corners of the UK do not benefit either directly or indirectly from the £9.8 billion total cost of the Astute programme—not least the maintenance on the south coast that the hon. Lady mentioned.

The current submarine build programme alone sustains more than 10,000 jobs across the UK, as we have heard. There are some 5,000 high quality and skilled jobs at nine BAE Systems sites across the UK and thousands more are supported through 400 suppliers across the country. Thanks to our commitment to build seven Astute class submarines, as set out in the strategic defence and security review, these people are set to be busy for years to come.

These are the biggest and most advanced attack submarines ever ordered for the Royal Navy and the first two have bidden farewell to Barrow to join their cousins at their base port, Clyde naval base. But the pace does not slacken. I have seen for myself the hive of activity that is the Devonshire dock hall, as the third boat, Artful, is set to follow closely behind. Construction of boats four, five and six is also underway.

It is easy to focus only on BAES in Barrow, but we should not forget that the power plant at the heart of every nuclear submarine—in the past, now and in the future—has come from the Rolls-Royce facility at Raynesway in Derby. Rolls-Royce has been central to our nuclear-powered submarine fleet for more than 60 years, as the only company in the UK with design and production capability in nuclear submarine reactor systems. We recently announced an investment of more than £1 billion, to ensure we retain this unique national strategic capability for many years to come. This investment will regenerate the facility and sustain reactor core production at the site, securing some 300 of the most highly skilled manufacturing jobs in the process.

Likewise, the fleet could not continue to operate without the support provided at Devonport dockyard, as the hon. Lady highlighted. The refuelling, refits and overhauls that are essential to keeping our submarines at sea are all carried out here, as the centre of excellence for submarine maintenance.

It is not only England that plays its part in the submarine programme. Quite apart from the vital work done in support of our operational submarines by the 6,700 personnel supporting operations on the Clyde, firms across Scotland are winning contracts in the supply chain for build and maintenance of the fleet. For example, as hon. Members from Scotland present in the Chamber are no doubt aware, the sensor support optimisation contract I signed recently with Thales UK in May has secured 50 high tech jobs in Glasgow, along with a further 250 in Crawley, Manchester and Somerset.

Thomas Docherty Portrait Thomas Docherty
- Hansard - -

The Minister knows that I am a huge supporter of the submarine programme. He has mentioned Scotland and is also aware of the seven now decommissioned submarines, lashed against the wall at Rosyth. If he has time, will he say a little bit about the plans for the end of their lives, and if not will he meet me, perhaps in the autumn, to discuss how that programme is progressing?

Philip Dunne Portrait Mr Dunne
- Hansard - - - Excerpts

I am afraid that I do not have time to cover that point, but I am more than happy to meet the hon. Gentleman in the autumn to talk about the disposal programme. We made an announcement recently. The hon. Gentleman knows that this multi-year challenge is being carefully monitored and managed by the Ministry of Defence.

The sensor support programme contract that we signed with Thales will provide support to the eyes and ears of the fleet, which includes periscopes, sonar and electronic warfare systems for both the current and future submarine classes, as well as vessels in our surface fleet.

Although the ongoing build programme and the support to the current fleet are the most visible signs of our continued investment, defence is all about planning for the future and we must look ahead to building the next classes of submarine, the subject to which the hon. Member for Barrow and Furness devoted most of his speech. I will attempt to deal with some of the questions that he posed, but will not cover all of them, as he may not be surprised to learn.

We have learned much about the importance of sustaining this supply chain from the 10-year gap in submarine production in the UK after HMS Vengeance was launched in the 1990s, which the hon. Gentleman mentioned in respect of delays to the Astute class. Having to re-establish a submarine design, build, testing and commissioning capability that had lain dormant for a decade had a serious impact on the delivery of the Astute class and economic ramifications in Barrow. This has been well documented, but it is important that we do not lose sight of these hard lessons. For this reason, the Astute programme is crucial to sustaining the skills and the work force we need to meet our clear commitment to retain and renew a credible, continuous and effective minimum nuclear deterrent.