High Speed Rail (West Midlands - Crewe) Bill Debate

Full Debate: Read Full Debate
Department: Department for Transport

High Speed Rail (West Midlands - Crewe) Bill

John Bercow Excerpts
Report stage & 3rd reading & 3rd reading: House of Commons & Report stage: House of Commons
Monday 15th July 2019

(4 years, 9 months ago)

Commons Chamber
Read Full debate High Speed Rail (West Midlands-Crewe) Act 2021 View all High Speed Rail (West Midlands-Crewe) Act 2021 Debates Read Hansard Text Read Debate Ministerial Extracts Amendment Paper: Consideration of Bill Amendments as at 15 July 2019 - (15 Jul 2019)
Rachael Maskell Portrait Rachael Maskell (York Central) (Lab/Co-op)
- Hansard - - - Excerpts

I beg to move, That the clause be read a Second time.

John Bercow Portrait Mr Speaker
- Hansard - -

With this it will be convenient to discuss the following:

New clause 2—Compensation scheme for tenants

‘(1) The Secretary of State must by regulations make provision for a scheme to compensate tenants adversely affected by the scheduled works.

(2) Regulations under this section may contain such supplementary, incidental, consequential or transitional provision as the Secretary of State considers necessary or expedient.

(3) Regulations under this section must be made by statutory instrument.

(4) A statutory instrument containing regulations under this section is subject to annulment in pursuance of a resolution of either House of Parliament.”

New clause 4—Independent peer review

‘(1) The Secretary of State must commission an independent peer review of the High Speed Rail (West Midlands to Crewe) project.

(2) The review must include consideration of the project’s—

(a) environmental impact,

(b) economic impact,

(c) engineering, and

(d) governance.

(3) In this section, “independent” means it is carried out by persons who are independent of—

(a) Government,

(b) HS2 Ltd, and

(c) persons contracted or subcontracted to carry out the scheduled works.

(4) In this section, a “peer review” is a review conducted by experts of equivalent professional qualifications, expertise and standing to the persons responsible for each aspect of the project set out in subsection (2).

(5) A report of the review in subsection (1) must be laid before the House of Commons within 12 months of this Act receiving Royal Assent.”

New clause 5—Non-disclosure agreements

‘(1) The nominated undertaker, or any subcontractors thereof, must not enter into any non-disclosure agreement with any party in connection with the scheduled works unless the assessor of non-disclosure agreements related to the scheduled works (“the assessor”) has certified that it is in the public interest.

(2) The Comptroller and Auditor General must appoint a person to be the assessor.

(3) The assessor must be—

(a) independent, and

(b) a current or former high court judge, higher judge or Queen’s Counsel.

(4) In this section, “independent” means independent of—

(a) Government,

(b) HS2 Ltd, and

(c) persons contracted or subcontracted to carry out the scheduled works.

(5) The assessor must undertake his or her work with a presumption in favour of transparency and public accountability in matters connected to the scheduled works.

(6) The assessor must review any non-disclosure agreement between the nominated undertaker, or any subcontractors thereof, and any party in connection with the scheduled works and in place before this section comes into force to certify whether it is—

(a) in the public interest, or

(b) not in the public interest.

(7) The assessor may not determine that a non-disclosure agreement is in the public interest for the purposes of subsection (1) or (6) except for the reason that it is justified because of exceptional commercial confidentiality.

(8) If the assessor certifies under subsection (6) that a non-disclosure agreement is not in the public interest that non-disclosure agreement immediately ceases to have effect.

(9) In this section, a “non-disclosure agreement” means any duty of confidentiality or other restriction on disclosure (however imposed).”

Rachael Maskell Portrait Rachael Maskell
- Hansard - - - Excerpts

May I thank you, Mr Speaker, for selecting the new clauses that stand in my name and those of my hon. Friends? When Labour envisaged HS2, it was a very different infrastructure project from what we see today. We recognised that the generations, particularly across the north and the midlands, needed far better connectivity. We wanted to regenerate the northern towns and cities of our country, and we saw the potential in the midlands to spark a new industrial age and how that was not being met.

After decades of disproportionate investment in London and the south-east, it was a Labour Government who saw how improved connectivity was needed to attract vital inward investment and to revitalise economies in the north. That is what Labour is about: creating high-quality jobs and opportunities to inspire a generation. It is in our name, Labour. Of course, we all knew that rebuilding connectivity had to start in the north, particularly with the east-west connections, to truly join up what is now aspiring to be the northern powerhouse. However, without the power of investment in the transport system, that will be nothing more than a soundbite. That is why Labour supports phase 2a, which will be the shortest leg of the route, at just 37 miles in total, and provide that vital north-south link, north of Birmingham to Crewe. Our support is not unreserved, though, and we believe colleagues should join us in the Lobby today to vote for Labour’s new clauses.