Selaine Saxby
Main Page: Selaine Saxby (Conservative - North Devon)(3 years, 2 months ago)
Public Bill CommitteesQ
Richard Silva: On the second point about the special purpose vehicles, whoever incorporates an SPV to develop a higher-risk project that the Bill is aimed at, ultimately the regulator will say yes or no. It is the regulator and the regulatory regimes for gateways 1, 2 and probably 3 —fit for occupation—that will ultimately say, “Yes, this process has worked. That SPV is fit for purpose and will deliver a solid product.”
The problem is what happens in the future if, God forbid, something slips through the net of the regulatory regime or fails. When these things do fail, you know about it only over time. The Bill extends the provisions of the Defective Premises Act 1972 so that you have 15 years to go after developers, as opposed to six. That is all well and good, but in the real world it will have limited or minimal impact—it will be the same—for anybody who needs to take advantage of that new provision.
The Bill’s proposed regulatory regime is robust—details will follow, obviously—but ultimately, the regulator can have sanctions on it. If a large plc housebuilder that has, historically, built mixed-used, large-scale developments—high-risk buildings, in the context of the Bill—through a series of SPVs, the regulator will have to have an opinion on that, I am afraid.
Q
Kieran Walker: I think the key lessons are really about getting information and clear lines of communication as quickly as possible. The introduction of the Bill is, as I have mentioned, welcomed by our members and the industry as a whole, because it gives clear a framework and responsibility for duty holders, as well as a process that I do not think we have had in the past. I do not think that is necessarily the fault of industry. In the past, it has almost been an assumption that A will follow B will follow C—that is part of the lessons learned. Mistakes have been made in the past, not just in the house building industry but across the piece, to be honest. The main lesson learned is that we should perhaps have had that framework sooner, but hindsight is a wonderful thing—we are where we are in that respect. Would you mind repeating the second part of the question, please?
Q
Kieran Walker: I think resource and expertise are a big part of this, as is generally having clear and defined methods and processes in perpetuity for the handover of buildings. In the past, we have seen quite loose arrangements in that respect, from developers to management agents. I also think that expertise and training the skills in the sector are important, not just in the latter ends of the building management side, but within local planning authorities, so that planning officers and planning departments understand better the implications of tall buildings, whether from an access perspective, an evacuation perspective or any other matter.
In the detailed design phase, as we will see moving forward, we will need to upskill very rapidly the expertise and resource within the regulator itself, because it is a very complex niche of the market—tall buildings, fire and structure are not just a black-and-white area; it can be quite grey. The upskilling of the workforce, from professionals right down to skilled trades, is one lesson that I think we can all learn.
Q
Kieran Walker: There could be more—I would be keen to see more and our industry would be keen to see more. There is probably more to come through secondary legislation on the duties of key roles and responsibilities, as well as on the golden thread. I agree that we could see more there.