High Speed 2 Reset

Ruth Cadbury Excerpts
Tuesday 19th May 2026

(2 months, 1 week ago)

Commons Chamber
Read Full debate Read Hansard Text Watch Debate Read Debate Ministerial Extracts
Ruth Cadbury Portrait Ruth Cadbury (Brentford and Isleworth) (Lab)
- View Speech - Hansard - -

I thank the Secretary of State for being honest with the House and for grasping the nub of the problem. We should not need the publication of the Lovegrove report or today’s statement to know that the cost and timetable overruns on HS2 started long before, because the previous Government wanted spades in the ground before the designs, costs and permits were ready. They then cancelled half the project, so we have the Aston to Old Oak Common project. I am glad that the Government picked that up and are moving ahead on the Euston element as well. We also had the Stewart review and the Oakervee report to tell us what went wrong.

My question is not actually on HS2, because the Rail Minister and the HS2 chief exec are coming to the Committee tomorrow, but on elements that are picked up in the Lovegrove report. What is the Secretary of State doing now to ensure that essential transport projects, starting with the lower Thames crossing and the Northern Powerhouse Rail project, do not go the same way? Will she assure me that she will not put on the high-vis and the hard hat for the photo opportunities until all the detail, permits and cost budgets are in place first?

Heidi Alexander Portrait Heidi Alexander
- View Speech - Hansard - - - Excerpts

My hon. Friend the Chair of the Select Committee is right that the problems of HS2 were born many years ago. The fact that the civil engineering was delayed for four years is not the product of decisions by this Government or the current management of HS2, but is, as she says, about overly optimistic cost estimates, construction starting before designs were mature, insufficiently controlled delivery, poor contractual arrangements, gold-plating, and constant changes in policy and scope. She is entirely right on that.

My hon. Friend asked me what lessons we are learning about the delivery of future transport infrastructure. On Northern Powerhouse Rail, we have worked closely with local leaders to agree scope, priorities and sequencing in advance, so that we know what elements of the overall programme will be delivered first. We have set an overall budget cap for that, and are securing local contributions to ensure that we maximise the economic and regeneration potential of the new transport infrastructure in those places. We are learning the lessons.