HS2: Revised Timetable and Budget Debate
Full Debate: Read Full DebateRobert Goodwill
Main Page: Robert Goodwill (Conservative - Scarborough and Whitby)Department Debates - View all Robert Goodwill's debates with the Department for Transport
(1 year, 9 months ago)
Commons ChamberI have the greatest respect for the hon. Member, and I served alongside him on the Transport Committee, but I take issue with him on there being no investment going into the north. The integrated rail plan is £96 billion of investment going to the north and the midlands. The HS2 statement commits to the completion of Old Oak Common to Curzon Street because that is where the construction is being delivered. It talks about a rephasing of two years on the section that goes to Crewe, and on the line from Crewe to Manchester—phase 2b—there is no change to the indicative timeline at all. Once phase 2b is delivered, we will see the benefits of Northern Powerhouse Rail, which we are committed to as well. I could not speak to projects in the south-east that are anything like those I have mentioned over the last minute, because the bulk of the investment in rail is going to the north and the midlands, and that will continue to be the case.
In the three years that I was the Minister responsible for HS2, almost a decade ago, I commissioned work to see whether we could deliver the project more quickly by opening Birmingham to Old Oak Common ahead of Euston. The result came back that around two thirds—certainly more than half—of passengers would be getting off at Old Oak Common anyway, to use the Elizabeth line to access places such as Heathrow airport and Canary Wharf. Does the Minister agree that Old Oak Common will, for the majority of people, be the London terminus that they use, even when Euston is open?
I am glad my right hon. Friend mentioned Old Oak Common, because following the Oakervee review, that was anticipated to be the station where services would commence from 2033. Despite what may have been said, it is interesting to look at what we are doing with Old Oak Common. It will be the best connected and largest new railway station ever built in the UK. It will have 14 platforms and be one of the busiest railway stations in the country, with access to central London and Heathrow via the Elizabeth line, and connections to Wales and the south-east. Importantly, it will also allow us to deliver trains to Manchester in one hour and 11 minutes, which is 54 minutes quicker than at present. That demonstrates that the whole country benefits from Old Oak Common.