Madam Deputy Speaker, may I extend my thanks to you and Mr Speaker for granting this urgent personal debate on waste incineration? Before I get going, let me declare to the House that my family run and operate a plastic recycling business. There is much to cover in this debate, so in the short time that I have, I want specifically to talk about the Aire valley incinerator that is due to be constructed in my constituency.

--- Later in debate ---
Robbie Moore Portrait Robbie Moore
- Hansard - -

On 8 December last year, the Environment Agency made the decision to award an environmental permit for a waste incinerator to be built in Marley, right on the outskirts of Keighley. The scheme was originally awarded planning consent by our local authority, Bradford Council, back in early 2017. That decision was in spite of huge local opposition. That opposition was led for many years by the Aire Valley Against Incineration campaign team, which is an excellent group. I must at this early stage in the debate give particular credit and extend my personal thanks to Simon Shimbles and Ian Hammond, who are part of the campaign team and have been working closely with me throughout the many conversations I have had, so that we can collectively raise our concerns. Their passion, dedication and acute attention to detail has shone throughout all our discussions.

This is a campaign team that has seen, over the last six years or so, its following and the involvement from local residents grow to over 6,000 people. The team has worked tirelessly over many years. In my view, since forming, they have represented the views of the many residents in Riddlesden, East Morton, Long Lee, Thwaites Brow, Keighley and our wider community far better on this subject than our local district council.

As I have indicated, I stand here in the full knowledge that the green light has been granted for the Aire valley incinerator to operate, so I want to pick up on some of the huge concerns that I and many others still have, and address some of the flawed decision making and disastrous decisions that have been adopted throughout the planning application and the environmental permit stages.

This is an incinerator that is to be built at the bottom of a valley in close proximity to schools, residential care homes, playing fields, people’s homes—spaces where children grow up and play. Yet despite that, and a huge number of other factors which I will go into, both the Environment Agency and Bradford Council, as the local planning authority, have deemed the construction and operation of the incinerator to be suitable and fit for our environment.

This has been a long-running issue. The environmental permit for the incinerator was granted last December, but the campaign against the project began way back in 2013. In October of that year, the very first planning application for the incinerator was made to Bradford Council. Four years and three applications later, the Labour-run and controlled Bradford Council granted planning permission. However, throughout this whole period, many residents, including my hon. Friend the Member for Shipley (Philip Davies), questioned time and again whether the planning applications were scrutinised by Bradford Council in enough detail.

I only entered this place in 2019. I have therefore taken the time to look back at Labour-run Bradford Council’s report, which was produced by its assistant director for planning for a planning committee that met in February 2017. The report included a recommendation to grant planning permission. I have a copy of that report here and it makes worrying reading. It concludes that there are no community safety implications. Bradford Council’s air quality officer registered no objection. The Environment Agency registered no objection at the planning stage, commenting that

“We…have established that there are no show stoppers or serious concerns relating to the location of the proposed development”,

despite it being in close proximity to many homes and situated in the bottom of a valley.

Richard Holden Portrait Mr Richard Holden (North West Durham) (Con)
- Hansard - - - Excerpts

I am facing a very similar situation in the Delves Lane area of my constituency at the moment, where I have just heard that the local authority, Durham County Council, has done a deal with a local developer to not put forward planning permission until after the local elections. Is not that exactly the sort of issue that we are facing with these proposals when they come forward: shady backroom deals, often dragged out for longer in order to avoid democratic scrutiny? My hon. Friend has rightly highlighted the issue he faces in his constituency.

Robbie Moore Portrait Robbie Moore
- Hansard - -

I thank my hon. Friend for his intervention. To be quite honest, I am not surprised and I find that an absolute disgrace to hear. We are talking about incinerators being developed right next to people’s homes, in close proximity to schools, care homes, and where people will be growing up and wanting to thrive in a sustainable environment. I am sorry to hear that he is experiencing a similar situation with Durham County Council.

The planning committee report made comments that concluded that planning permission should be granted. I quote another worrying statement:

“The proposal addresses the waste needs of Bradford community in proximity to the waste arisings.”

Given that Keighley is situated on the periphery of Bradford district, that is factually incorrect. So I say to Labour-run Bradford Council: Keighley will not be treated as your dumping ground.

The report goes on:

“The proposal enhances the environment and”—

wait for it, Madam Deputy Speaker—

“promotes recycling.”

That is complete and utter nonsense. How on earth can burning waste be classed by Bradford Council as enhancing the quality of the environment, when it is known that particulate matter such as sulphates, nitrates, ammonia, sodium chloride and black carbon enter the atmosphere from such a process? I can only conclude that the council must be taking us in Keighley for fools. And then to go on to say that the incinerator, which burns waste, promotes recycling—that goes beyond taking the biscuit.

Following Bradford Council’s planning approval, the applicant, Endless Energy, applied to the Environment Agency for an environmental permit, triggering a two-stage consultation process, with the second consultation taking place just last year. The Environment Agency promoted that it was “minded to approve” the permit—again, all this despite the valid concerns that had been raised by residents, the Aire Valley Against Incineration campaign team, my hon. Friend the Member for Shipley and myself.

If that was not bad enough, the Environment Agency decided to hold its supposedly open and transparent consultation right in the middle of a pandemic—a consultation, I might add, that took place wholly online, denying my residents with no digital connectivity or internet access the ability to contribute. That consultation contained over 50 documents for the general public to review, yet, due to the pandemic, those documents were not made publicly available in local libraries or community spaces as one would typically expect. I raised my concerns, and admittedly extra time was granted by the Environment Agency for the consultation, but the stark reality is that members of the public from my constituency and beyond were given an inadequate chance to properly scrutinise the proposals and properly comment on the concerns regarding air quality that they had originally raised.

I want to provide some clear examples of the Environment Agency’s failings to be open and transparent throughout this process. The campaign team experienced significant delays in respect of freedom of information requests. Under the terms of the FOI regulations, the Environment Agency is required to reply within 20 working days. The worst example experienced by the campaign team was a delay of four months. That is completely unacceptable. It resulted in a lost opportunity to carry out proper scrutiny of the applicant’s information.

Here is a second example: there were missing documents that were not made available to the public at the start of the second consultation. Copies of all five of the EA’s notices sent to the applicant were omitted, meaning that the public could see only the answers from the applicant and not the questions that the Environment Agency asked. Those missing documents were made available only when I and the campaign team asked for them.

To be frank, that is shoddy work from a regulatory body, and I cannot express my frustration and anger enough. I am exceptionally pleased that the Under-Secretary of State for Environment, Food and Rural Affairs, my hon. Friend the Member for Taunton Deane (Rebecca Pow), who I know cares deeply about ensuring that our regulatory bodies do their job properly, is listening and is able to take on board the challenges that we have faced. My constituents deserve much better

The potential impact on people’s health of the incineration process cannot be ignored. In a 10-page submission that my hon. Friend the Member for Shipley and I jointly submitted to the Environment Agency, we raised the following concerns: issues with the inadequate and unfair consultation process itself; concerns about noise and odour pollution; and concerns about the fact that the incinerator is built at the bottom of a valley, the resultant challenges of the topography, and the public health implications of emissions as a result of temperature or cloud inversions.

We also raised concerns that pollution modelling used unreliable data. I will give an example. The Environment Agency used data from the Bingley weather station. The Bingley weather station is located 262 metres above sea level, whereas the proposed Aire valley incinerator is situated roughly 85 metres above sea level. That discrepancy in evaluation means that the estimated dispersal of emissions from the incinerator is based on information from a weather station in a significantly raised position, where wind speeds behave much differently from those experienced at the bottom of the Aire valley.

We raised concerns about the proposed monitoring of emissions and any enforcement action that is likely to follow. We raised issues with the stack height. The incinerator is proposed to have a stack height—a chimney height—of only 60 metres, yet other comparable incinerators have stacks far higher, where emissions are better dispersed.

I could continue—the list goes on—but perhaps the most significant of our concerns is the impact the incinerator will have on human health via air quality. The Minister will be aware that, back in 2018 and 2019, Public Health England funded a study to examine emissions of particulate matter from incinerators and their impact on human health. The study found that, while emissions of particulate matter from waste incinerators are low and often make a small contribution to ambient background levels, they make a contribution nevertheless. Of course, there are many variables and influencing factors, such as the stack height, the surrounding topography, the feedstock, the microclimate—again, the list goes on.

Residents are rightly concerned—I share their concerns—about the impact on air quality, not just from the incinerator itself but from the increased traffic flows bringing waste to the site. Unbelievably, in questioning the decision making for the award of the environmental permit, I was told by the Environment Agency that it could consider only the emissions from the incinerator itself, not those from the increased traffic flow from the heavy vehicles that will bring the waste to the site, because that was a planning matter, which Labour-run Bradford Council had already considered and deemed to be acceptable.

It is my strong view that my constituents have been let down: failed by our Labour-run local authority, which claims to have its residents’ best interests at heart, but also let down by the Environment Agency, a regulatory body that, in my view, carried out a half-hearted attempt through its consultation process. May I use this opportunity to urge my hon. Friend the Minister to do all in her power to take a close look at the Environment Agency’s involvement, to hold it to account and to ensure that it fulfils its statutory duty and that its involvement in such consultations takes place in a proper manner?

I want to use the last few moments to talk about the role of incineration in general, and about the circular economy. The circular economy means prioritising, reusing, repairing, refurbishing and recycling existing materials and regarding waste as something that can be turned into a resource. Many of us in this place and beyond will be familiar with the waste hierarchy, which gives top priority to preventing waste in the first place and, when waste is created, gives preference to preparing it for reuse, then for recycling, then for recovery and last of all for disposal, whether to landfill or waste incineration. As the Minister will be well aware, I believe that all Government policy should be based on this hierarchy.

I am pleased to see the extensive work that has gone into the Environment Bill, led by my hon. Friend the Minister, and also into the Government’s resource and waste strategy. I was proud to sit on the Environment Bill Committee and see that piece of legislation work its way through this House. I look forward to getting involved in more of the debates as it comes back to this Chamber. It is my firm view that if we are serious about investing in our circular economic model, we must, as a country, incentivise reuse, recovery and recycling practices. Of course I appreciate that some waste simply cannot fall into those categories, but we must do all we can to discourage incineration and landfill practices as the preferred option.

That brings me on to the introduction of an incineration tax, which is something that I have raised in this place before, and I commend this option. Unlike incineration, landfill is already subject to a tax, and an incineration tax could work in a similar way. It would be a fiscal de-incentivisation to incineration and could lead to more innovation in other practices, such as recycling. Of course, an incineration tax is not new or radical. Other countries have already adopted it, including the Netherlands, Sweden and Austria.

We owe it to the next generation to ensure that the planet is left safe and in a much better place than we found it. However, building more incinerators such as the Aire valley incinerator, the one in my constituency, goes against everything we are trying to achieve. I know that many other colleagues from across the House are of the same view. I suspect that it will be a couple of years before the Aire valley incinerator is built and becomes operational, and I dread the date, but I wish to reassure all residents in my constituency that the campaign to stop it is by no means over. I will do all I can to ensure that their voice is heard, and to ensure that the operator, and those overseeing it—Labour-run Bradford Council and the Environment Agency—are watched like a hawk. I will ensure that their actions are scrutinised every step of the way.