Restoration and Renewal of the Palace of Westminster Debate

Full Debate: Read Full Debate
Department: Leader of the House

Restoration and Renewal of the Palace of Westminster

Nigel Evans Excerpts
Thursday 20th May 2021

(2 years, 11 months ago)

Commons Chamber
Read Full debate Read Hansard Text Watch Debate Read Debate Ministerial Extracts
David Amess Portrait Sir David Amess (Southend West) (Con) [V]
- View Speech - Hansard - - - Excerpts

I was shocked and saddened to learn of the death of our former colleague Mike Weatherley. I offer my deepest sympathy to his family and friends. He was an outstanding colleague and Member for Hove.

Having been a Member of Parliament for a long time, I fully understand, better than most, the need for restoration work to be conducted. I could actually do with some myself. Although I was greatly heartened by the opening statements of my right hon. Friend the Leader of the House, I take nothing for granted. There are so many potential fire hazards around, not to mention the unsanitary state of the place generally.

When I was a member of the Administration Committee, we were taken up the Elizabeth Tower to see for ourselves how urgently the repair work was needed. Water was pouring in through the windows and the masonry was in a very poor state. As the scaffolding is gradually being removed, we can all see the transformation that has taken place, with the minimum of disruption to the work of the Palace of Westminster. This project should be taken as an example of what can be achieved without interruption to the life of the parliamentary estate. Will my right hon. Friend tell me when the project will be completed and the whole tower will be revealed?

The Palace of Westminster, as many colleagues have said, is a symbol of democracy the world over, and the envy of most other countries, but behind the façade there is severe decay. Over the past few years, there have been several instances of pieces of stonework falling from the building, endangering staff and visitors. The sewers are no longer functional. The smell along the Terrace Corridor is absolutely appalling. One need only visit the cellars, as I have, to realise the very real fire risk from the miles of electrical cabling. Electrical wiring has been added in layers over many years until it hangs like jungle creepers everywhere. A modern Parliament needs modern services, and a full upgrade is long overdue.

As a member of the all-party fire safety and rescue group, I regularly receive reports on the number of minor fires that are dealt with every month as a matter of routine. Over the past few years, much has already been done to improve fire safety. Thousands of new sprinklers have been installed, along with miles of pipework to service them. Thousands of automatic fire detection devices have also been fitted, along with voice alarms. All this has been done without disturbance and almost without the knowledge of Members and their staff. I do not think any Member would wish to see this magnificent building share the same fate as Notre Dame. The roof is leaking and stonemasonry needs restoring, not to mention the problem of the asbestos that needs to be safely removed.

I therefore accept without reservation the need for action. What I remain unconvinced by is the proposition—because it is still there—that the elected House should move out of the building. I fear that Parliament may never return, in spite of all the guarantees given.

The plan voted on by the House of Commons recommended a full decant and the provision of a temporary Commons Chamber in the courtyard of Richmond House. May I point out that the vote was extremely close—but I fully understand that every vote counts—with a majority of only 16? That is not exactly an overwhelming endorsement. Apparently, these plans, as we have heard, have now been shelved and there is a new plan to completely demolish Richmond House and rebuild it. This is not only a horrendous waste of money and time, but totally unnecessary. Demolishing a perfectly serviceable, thermally efficient, relatively modern listed building to accommodate a temporary Chamber is absolutely crazy. The so-called gold-plated solution, which seeks to create an exact replica of the Commons Chamber, is a ridiculous idea. It is also costly in terms of emissions, given the Government’s pledge to reach net zero carbon emissions by 2050. Demolishing the building and rebuilding it is not only a complete waste of money, but would result in unnecessary additional carbon emissions.

Richmond House, a grade II listed building, where I worked in my days as a Parliamentary Private Secretary, is barely 35 years old—I was there on the day it opened—and to consider demolishing it is an absolute act of vandalism. It also delays the start of the restoration and renewal work for several years, possibly until 2027. Work should start as soon as possible to renew the hazardous wiring and other services in the Palace and to create a modern, sustainable working environment within the historic fabric of the building.

Since the vote in 2016, there has been a considerable change in the make-up of the House and the arguments for and against a full decant need to be looked at again. The Sponsor Body needs to be held to account by the elected members and its proposals properly scrutinised. I think the unelected Chamber should be the ones to decant, if that has to happen, as they have done admirably well during the covid-19 pandemic—it would probably be my only opportunity to sit on those red Benches. Hybrid or fully virtual proceedings have worked well for them over the last year, so I have favoured us using the Lords Chamber while the Commons and surrounding areas are restored. The work on the services for the whole Palace, including the cabling in the basement, could then go ahead with a minimum of disruption to Members and their staff. The Lords Chamber and the Royal Gallery can be serviced externally in terms of electricity, lighting and so on, which would provide enough working space and eliminate the need to convert the QEII Centre for the use of the House of Lords at an estimated cost of £350 million or more. The estimates of cost for the conversion of the QEII Centre did not take into account the loss of earnings for this publicly owned building and the subsequent loss to the Exchequer. Plans for the QEII Centre also include major building works to create a working space to replicate the height of the Lords Chamber—it is absolutely ridiculous.

Since 2016, with the uncertainty of Brexit compounded by the covid-19 pandemic, money is now very tight, so the economic considerations are absolutely crucial. Affordability and value for money are so important. The Chancellor has said that huge efforts need to be made to balance the books after the enormous cost to the public purse of supporting businesses throughout the pandemic. The current plans will cost billions, and I think we need to take into account the sacrifices made by our constituents over the past year and think of how it will look to them if we allow taxpayers’ money to be wasted on a white elephant. By comparison, the cost of a new school is between £20 million to £30 million, so we need to be both careful with costs and transparent in how the money is spent.

Both Houses have proved their ability to work flexibly and embrace new technology over the past year, which is what I am doing right now. It is only right that all options be looked at in order to save millions of pounds of public money and start the process of renewal as soon as possible. Virtual proceedings are not ideal, but all options need to be considered.

I do not want the Sponsor Body to be given a blank cheque. Elected Members should have oversight of the budget for this project. The recent strategic review has costs redacted, even in the copies provided to Members of Parliament. Every solution presented so far by the body inflates the costs and increases the delay in commencing the urgent work that is required to make the Palace safe for everyone who works in and visits the building.

If a temporary Chamber is required, there are cheaper and less disruptive options available, and Members of Parliament should be given the chance to debate them. The House should take this opportunity to rethink plans for a full decant and instead consider a rolling programme of work on the Palace structure and services, working continuously in three shifts. It could be completed in five years, and the continuity of Parliament in this place maintained. The current plans in no way represent value for money, the importance of which was stressed in the Act of Parliament that set up the Sponsor Body.

Some Members of Parliament serve only for one term. My length of service, together with that of a number of colleagues who have spoken in this debate, is quite unusual these days. I will never forget walking into this building on my first day as a new Member of Parliament—even if some people mistook me for a Labour Member. The magnificence of the architecture and the weight of history that these walls carry was quite overwhelming. To deny the next generation of Members of Parliament that experience, and instead to swap it for a soulless copy of the Commons Chamber in another building, would be absolutely unforgivable.

Nigel Evans Portrait Mr Deputy Speaker (Mr Nigel Evans)
- Hansard - -

Thank you, Sir David. You mentioned the architecture of this building, which is vital, but it is the people who make this building. Mike Weatherley was one of those people, and I counted him as a personal friend. He told me that he was standing down because he did not want to leave it too late to start another career. He did start another career, and he did it admirably well, travelling between California and the United Kingdom. I was devastated to learn of his illness, and more so this morning when I learned of his passing. My deepest condolences to his family.

--- Later in debate ---
Jacob Rees-Mogg Portrait Mr Rees-Mogg
- Hansard - - - Excerpts

I am absolutely at one with the hon. Lady, and I am grateful for that helpful intervention. That is why the outline business case is being worked on now. We hope to have some preliminary idea about it early next year, with the vote on it in 2023.

Let me return to some of the individual contributions. My neighbour and right hon. Friend the Member for North Somerset (Dr Fox) emphasised the symbolism, the need to get on with things and the stonework. It is important that, under the Act, the Commission—I can assure the House that the Commission is very aware of this—is allowed to carry out repairs before the R and R body takes over. We have scaffolding up, so it seems sensible to try to do repairs where we can. There is no point in having scaffolding, as it currently is, just acting like the slips, waiting to see what catches come its way, although of stonework rather than cricket balls. So I agree with what my right hon. Friend said.

The hon. Member for Huddersfield (Mr Sheerman) seemed to want to become Old Father Thames, which was a rather charming way of suggesting how we should rebuild the Palace. My hon. Friend the Member for Clwyd South (Simon Baynes) emphasised the limits on public money, as did the hon. Member for Strangford (Jim Shannon). He also encouraged, as did many others, UK-wide working and opportunities, and pressed for answers on timescales, which we will get in the outline business case.

I find myself in a very high level of agreement with my right hon. Friend the Member for Basingstoke (Mrs Miller), who pointed out that this is a place of work. Although it is nice that tourists come to see it, that must not interfere with its work as a legislature, and if we need to do building work in August, it cannot be open to the public in that time. Getting that priority right is very important.

My hon. Friend the Member for Mole Valley (Sir Paul Beresford) said, “Get on with it!” I hope that I have persuaded him that we are getting on with it, and that is what everybody wants to do. As I have set out, the preliminary works are very much already happening.

My hon. Friend the Member for Southend West wanted a date for the Elizabeth Tower, and I will give him a date. I am told that the bells will ring in early 2022. Now, “early”, when used by the civil service, is one of those things that I have learned about in my brief time in Government, and early 2022 could mean some time in December, but it would be early December. However, there is a better promise, which is that the scaffolding will be down by summer 2022—“summer”, of course, is an equally elastic term. What particular point in summer, I do not know, but we are almost there. The bells were being tested this morning, and it was really rather wonderful to hear them—it was uplifting. My hon. Friend made the crucial point, which was so helpful to the argument, that the Richmond House planning would have delayed us until 2027, which would have been an added complication and problem with the whole programme.

My hon. Friend the Member for North Norfolk (Duncan Baker) brought his own experience to bear in a very interesting way, and talked about how we look after customers. He said that we do not inconvenience them, but that we sometimes have to recognise the need to keep going regardless.

My hon. Friend the Member for Bishop Auckland (Dehenna Davison) made an inspiring and sparkling speech. She was against gold-plating, as am I, and did not want a blank cheque in these economic circumstances. She reminded us of Churchill’s view of how buildings shaped our democracy. She also talked about what it would look like to our constituents if we decided to do things in a sort of Liberace way—I am not very keen on doing things in a Liberace way. [Interruption.] I am being mobbed out from the Front Bench by the Deputy Chief Whip. As he has 330 votes in his pocket, I must not ever dare to disagree with him; otherwise, Government business might become problematic.

My hon. Friend the Member for West Bromwich West (Shaun Bailey) mentioned opportunities and the need for there to be a plan for jobs. I think his basic plea was for every member of his constituency to be employed on the parliamentary estate. He referred to apprenticeships. Apprenticeships will be important and will have a long-running benefit for the heritage of this country because the stonemasons who are trained here will then be stonemasons who work on our great cathedrals and other heritage buildings.

My hon. Friend the Member for Hyndburn (Sara Britcliffe) mentioned the symbolism of this place and told us very clearly—I think this is the right way to put it—that we cannot duck the question. If we duck the question, we will end up grousing, to carry the bird thought through. But that is what we are doing now: we are not ducking the question.

I was delighted that my hon. Friend the Member for Sedgefield (Paul Howell) spoke. I fear that even now, nearly 18 months after the general election, one’s heart still leaps at the thought that Sedgefield is a Conservative seat. Leaving that little point aside, he mentioned what an iconic institution this is with its 1 million visitors. Follow the cash, as his old boss used to say to him, is what we must definitely be doing. The important point is that it is very hard to future-proof in terms of technology, because we think we are future-proofing but the technology goes off in some other direction that we did not think about. So we have to be open to a variety of opportunities.

This is a long-term project and it will come at very considerable cost to the taxpayer. The solutions we arrive at must therefore be the best option for the preservation of the Palace of Westminster and in the public interest, prioritising value for money. This is fundamentally a parliamentary project. I cannot remember who said that actually it is a fundamentally House of Commons project, because the symbolism of this House as the democratic House is what people think about when they look at the Palace of Westminster. I have the greatest admiration and respect for their lordships, but when people look at this palace, they think of the home of the world’s oldest democracy. My right hon. Friend the Member for North Somerset made that fundamentally important point. It is a parliamentary project. It is a House of Commons project. We are the ones who are accountable to taxpayers.

I have set out my Government’s views and other hon. and right hon. Members have set out theirs. I am confident that the restoration and renewal programme team will listen to those carefully, and in the coming months the Sponsor Body will engage with MPs and peers to seek their views on how the proposals should develop. It is vital that parliamentarians give their time, energy and expertise to this process so that collectively we shape a programme that safeguards both the Palace of Westminster and taxpayers’ money, and will make St Peter proud.

Nigel Evans Portrait Mr Deputy Speaker (Mr Nigel Evans)
- Hansard - -

If there is a Liberace candelabra going spare, I can think of no more fitting place than the Leader of the House’s modest office.

Question put and agreed to.

Resolved,

That this House has considered the restoration and renewal of the Palace of Westminster.