Nuclear Energy (Financing) Bill (First sitting) Debate
Full Debate: Read Full DebateMatthew Pennycook
Main Page: Matthew Pennycook (Labour - Greenwich and Woolwich)Department Debates - View all Matthew Pennycook's debates with the HM Treasury
(3 years, 1 month ago)
Public Bill CommitteesQ
Michael Waite: We are currently very active in the Czech Republic, Poland, Ukraine and so on. Those nations predominantly have either majority Government-owned utilities developing nuclear projects or Government financing for up to 100% of the project. They are reducing the cost of capital by fully leveraging Government financing, which is the cheapest financing. Those are absolutely all regulated approaches. No projects that we are doing currently rely just on market forces to develop nuclear; it is too much of a long-term project, with massive long-term benefits, to leave it up to the market.
I have a series of questions relating to—
Before you start, Mr Pennycook, I should say that we have five people asking questions and 12 or 13 minutes left, so can everyone be swift in their questions and answers?
Q
Julia Pyke: CGN currently has a 20% shareholding in Sizewell C. No material supply chain contracts are in place or intended to be in place with the Chinese supply chain or CGN. Whether CGN chooses to invest at financial close, and the extent to which it chooses to invest, is a matter for CGN itself and the UK Government. As Virginia’s question elicited, the RAB model is designed to bring in a lot more British financing and reduce reliance on overseas investors.
Q
Julia Pyke: That is absolutely a question for the Government.
Q
Julia Pyke: I think that Sizewell C can raise money under the RAB model. How CGN intends to go forward with a financial investment in Sizewell C is a matter for CGN and the Government.
Q
Julia Pyke: I think that the Bill is a great framework under which there is a lot of detail to be developed, and we would expect more detail to be developed in relation to designation and the conditions of eligibility. While I could hardly deny that the cost of nuclear builds has had some uncertainty in some cases, what is not uncertain is whether nuclear works and the technology works. I think there are no cases worldwide of nuclear projects that have been abandoned for technical reasons. The industry knows how to make nuclear power stations work. So I think that there is a degree of uncertainty about the exact cost, but the whole point of building a replica of Hinkley is to minimise that uncertainty, benefit from all the lessons learned and get nuclear on to a stable, repeat-build footing.
David Powell: We designed our SMR BWRX-300 on the basis of proven technology. So we know very much the cost base for that technology, and it is really in our interest and that of investors to ensure that we can deliver to time and to budget on that. With respect to the build, we would obviously want to try to minimise any impact and risk of cost and schedule overruns, because we see this as building a fleet of smaller reactors out of a more modular-type approach.