HS2: Revised Timetable and Budget Debate
Full Debate: Read Full DebateMaggie Throup
Main Page: Maggie Throup (Conservative - Erewash)Department Debates - View all Maggie Throup's debates with the Department for Transport
(1 year, 9 months ago)
Commons ChamberIf there were no commitment to Manchester, the Bill Committee would have been disbanded, but it continues to go ahead for section 2b, and the indicative timescales remain exactly the same for the Crewe to Manchester piece. Its delivery is crucial to Northern Powerhouse Rail. That is why nothing has changed for 2b. I gently add, having been to see the engineering projects for the trans-Pennine route upgrade, that billions are being spent through the Pennines towards York to fully electrify that line, because that is where the bulk of our investment is geared—to the north and the midlands.
Over the past 40 minutes, the Minister will have realised that one of the big issues is blight. What steps is he taking to ensure that those residents who remain blighted by the original HS2 routes, such as those in my towns of Long Eaton, Sandiacre and Stanton Gate, are fully compensated now that their properties are no longer required for the revised route?
The line of route remains the same. There is a two-year rephasing of the section up towards Crewe, but the line of route remains the same as when it was announced. My hon. Friend is right that many constituents have experienced issues as a result of the impact on HS2. The process in place with HS2 ends up in appeals in the Department for Transport. I look at those individual cases, as does the Secretary of State. In some cases, although those constituents may not be strictly entitled to the cost of moving, we have looked at them and decided that their health impacts necessitate a payment and assistance from the Department. I will continue to work with my hon. Friend and all hon. Members to help their constituents.