Lords ChamberMy Lords, I am sorry to spoil the consensus but I really feel as though this is Groundhog Day. I cannot believe that we are proceeding with something so obviously discredited and which is probably about to be scrapped, with all the costs and damage involved. All my remarks apply to any HS2 scheme in its entirety.
The original concept of HS2 was built on speed. When this proved impractical, the selling point became capacity. This has now become discredited not because there is no need for extra capacity but because this railway line is clearly not where it is most needed. Costs are now completely out of control, completion dates are a joke and any idea of accountability or normal public and parliamentary scrutiny has long since been abandoned. Whistleblowers are now revealing just how bad the situation is and, despite desperate attempts to muzzle them, the truth is coming out. I understand that the whole question of fraud is now being investigated.
With little effort being made to remedy the situation, a committee of your Lordships’ House suggested to HS2 that it consider reduced speed, since this makes all kinds of sensible savings. It also asked HS2 to stop the line at Old Oak Common rather going into Euston, which has proved an intractable problem. Neither of these suggestions was taken up. HS2 carries on in its own chaotic, spendthrift way. This is not surprising since, when the previous Secretary of State for Transport was asked how much he was prepared to spend, he said, “What it takes”. What saddens me and makes me resist this Second Reading is HS2’s pig-headed unwillingness to listen to or take advice from anyone, no matter how qualified they are.
Nothing has changed since I put down my amendment in your Lordships’ House at Third Reading of the HS2 Bill in January 2017, which would have stopped the farce once and for all. I said on that occasion:
“This House has a simple choice before it this afternoon. If it believes that the HS2 project provides good value for money and will benefit the British public, it will vote against the amendment. But if it agrees that this was an ill-conceived project from the start, which has been entirely discredited, even during the three years it has been passing through Parliament, and that if allowed to proceed, it will result in massive expenditure and huge disruption in both London and the countryside for no discernible benefit at all, the House will support the amendment and stop this scheme before any … harm is done”.—[Official Report, 31/1/17; col. 1099.]
Sadly, my amendment was rejected and we have since had two and a half years of wasted money and damage to homes, lives and the environment. I did have some support from people who really understood the situation: the noble Lords, Lord Macpherson and Lord Burns, both Financial Secretaries to the Treasury when HS2 was being put through. Asked to explain his vote, the noble Lord, Lord Macpherson, said that it was,
“simply on value for money grounds. In a world where capital spending is rationed, there are many road … schemes which would give the taxpayer a better return”.
Other signatories, including the noble Lord, Lord Burns, also backed the move.
Not only must the House not proceed with the Bill, but the existing work on HS2 must be stopped before any more damage is done, particularly to our environment and to people’s lives, homes and businesses. It is criminal to be felling trees in preparation for something that probably is never going to be built. In a recent statement on HS2 in the other place, Jeremy Wright MP asked,
“may I press the Secretary of State on the point he made about enabling works? As he knows, there is more than one kind of enabling work currently under way. Some of the enabling work is the destruction of ancient woodland sites. There are seven of them in my constituency, along with a very old and much valued pear tree in the village of Cubbington. Given that he has announced an all-options review, including the possibility that this project will be cancelled or significantly revised, surely it is possible and sensible to categorise those types of enabling work that will do irreversible damage and postpone them until the review has concluded”.—[Official Report, Commons, 5/9/19; col. 356.]
In a similar vein, I have seen a plea from Councillor Kathy O’Donoghue concerning the section through Cheshire. She is extremely worried about what is happening in Cheshire, where there are now all sorts of problems. On 8 October, a planning application is going to be heard by Cheshire West and Chester Council to build a compound, which will have a huge effect on the area, where there are old salt mines. She is concerned that the planning application and the compulsory purchase order might go through before it has been decided that the project will proceed.
I was recently part of a judging panel in a competition to find alternative ways of spending £58 billion on our railway system. It was truly amazing to discover what a difference could be made nationwide, particularly in the north, with links east and west. In summary, we must call a halt to the existing work, particularly preparatory work, and immediately review the current position, as we are doing. We must spend every penny available for our railways on sensible, well thought out schemes. For heaven’s sake, we must find a way of costing these major infrastructure projects properly and supervising their construction in a sensible and professional way.
My Lords, I congratulate the Minister on her opening speech. As I will point out in a moment, there is a big problem with the conflict between that speech, which was full of enthusiasm, and the setting up of a fundamental review, which could lead to the cancellation of HS2. There is a clear left hand/right hand problem in the handling of this project at the moment, which will only serve to add to costs and delays. None the less, the noble Baroness’s speech was excellent and set out the whole case against having a fundamental review of HS2. My noble friend Lord Berkeley who, to my amazement, has agreed to serve on this extraordinary review, is not in his place this afternoon. However, I will recommend that he reads that speech and ceases his work forthwith. I also note the presence in the Chamber of the noble and learned Lord, Lord Walker of Gestingthorpe, who chaired the hybrid Bill committee on the London to Birmingham Bill. With the scale of the work required and the dedication of its members, that was one of the most heroic endeavours which any noble Lord has undertaken in recent times. It showed this House at its very best. I am looking around the Chamber to see who will be volunteering for the next hybrid Bill committee. My noble friend Lord Snape is nodding; maybe he will chair that committee. We would certainly welcome that.
The noble Lord’s work played a very significant part in taking this big infrastructure project forward, as did the work of the noble Lord, Lord Birt, when I became Secretary of State for Transport and devoted myself in a serious way to looking at the case for high-speed rail. He and the noble Lord, Lord Teverson, referred to France, but of course it is 55 years, more than half a century, since the Japanese opened their first and transformational high-speed line between Tokyo and Osaka. They started construction 60 years ago, so we have been taking some to catch up, but it was the noble Lord’s strategic review which put it in my mind that I should be looking very seriously at the case for a high-speed rail network in this country. This is a very good example—and we do not have many, I fear, in this terrible Brexit crisis—of constructive public policy which is factually based, learns from evidence and learns from international experience. As the noble Lord, Lord Teverson said, almost all the rest of the industrialised world, apart from the United States, has high-speed rail, and even the US is halfway through constructing a line from San Francisco to LA.
The noble Lord mentioned China. China has more high-speed rail than the rest of the world put together and has been building a network at great speed. When I was Transport Secretary the Chinese Transport Minister offered to build our high-speed line. He said to me over a very long dinner in the Transport Ministry in Beijing that he would build it for half the cost of the Germans—I assume that he assumed we were about to give a contract to the Germans. I said, “We have this thing called Parliament, Minister, and it has to agree to all this before we can start the construction, but by all means let us have a conversation in a few years’ time”. I regret to tell your Lordships that that Minister is now in jail under a suspended sentence of death for corruption, so although the Chinese are able to construct these projects quickly, there are downsides in the way they conduct their affairs in Beijing. I am glad that I am with your Lordships and not currently at Her Majesty’s pleasure.
The background to this is a great sense of urgency, as the noble Lord, Lord Birt, said, to see that our infrastructure matches that of other industrialised nations, all of which, apart from the United States, have been investing in high-speed rail to link their major conurbations. When the noble Lord, Lord Framlingham, said that this has been conducted without parliamentary consent and scrutiny, that is, of course, palpably untrue. There have been exhaustive debates. The work of the committee of the noble and learned Lord, Lord Walker, and that of the Select Committee in the other place was absolutely exhaustive.
I am not sure that I said it had been conducted without parliamentary consent, did I?
It is important to be accurate, with great respect to the noble Lord. He said that I said it had been done without parliamentary consent.
I did not. I said, “without proper parliamentary scrutiny”. There has been massive parliamentary scrutiny of this project. The Motion the noble Lord referred to, which he moved at Third Reading in January 2017, attracted 25 votes while there were 385 votes on the other side, so I do not think anyone can say that it is not the express will of Parliament that is leading HS2 to proceed.
The problem we have at the moment is, as I say, a left hand/right hand problem. On one hand, Parliament has given emphatic consent to this project to continue, and indeed to be authorised in the first place: not just the first phase, which passed this House by 385 votes to 25, and passed the House of Commons by 399 votes to 42—absolutely colossal majorities—but this Bill, extending HS2 from Birmingham to Crewe, was passed in the House of Commons in the middle of July by 263 votes to 17. There has been cross-party consensus and overwhelming support.
The Minister referred, and I assume that her officials were giving her very carefully crafted drafting in this respect, to the work taking place on HS2 as “preparatory work”. There is nothing preparatory about the work being done on HS2 at the moment. The line is being built; more than £5 billion has been spent and more than 1,000 people work at HS2 Ltd in Birmingham. If your Lordships go to Euston, you will see that it is not preparatory work that is leading to the virtual closure of the station, with huge tarpaulins up and big excavation works, but the construction of the railway line. It is right that this should happen, because, unless we start constructing it, it will never be there.
Parliament authorised this project to proceed two years ago. Billions of pounds have been spent, thousands of people are working on it—we expect this work to proceed. It is this that makes the review that has been set up so bizarre. At the same time as Parliament has given express and overwhelming authority for this work to proceed, thousands of people being employed and billions of pounds having been spent, what do the Government do, courtesy of the Prime Minister? They parachute in a fundamental review which is essentially conducting open-heart surgery on a moving patient, if I may mix my metaphors.
This whole project is being constructed, massive public expense is being entered into, and what do the Government do? They announce a strategic fundamental review, looking not just at the management of the project, which is absolutely appropriate to look at because it has not been good enough and is part of the reason we have the cost overruns, but the whole case for HS2, which has been approved by Parliament by majorities of more than 10 to one.
I see the clock is flashing, but I will carry on for a few more minutes because this is Second Reading.
There is not a fixed time limit. I will make two more points if I may.
When the noble Lord, Lord Framlingham, said that the case for HS2 when it started was on speed and not capacity, that was completely untrue. I published the White Paper on HS2 in March 2010, the opening words of which were,
“the Government’s assessment is … That over the next 20 to 30 years the UK will require a step-change in transport capacity between its largest and most productive conurbations … alongside such … capacity, there are real benefits for the economy and for passengers from”—
Will the noble Lord give way, since he is determined to take up the time of the House that nobody else, I am sure, will take up? Does he understand that the title of this project is “High Speed Rail”?
It is a high-speed line, but from the beginning the prime case for HS2 has been additional capacity. I was reading the opening words of the White Paper, which continue,
“alongside such additional capacity, there are real benefits for the economy and for passengers from improving journey times and hence the connectivity of the UK”.
My final point is about the network effects which my noble friend on the Front Bench referred to. HS2 will be a crucial part of a new and upgraded national transport network. It will link into Crossrail in London through its junction at Old Oak Common; it will link in with three airports—Heathrow, which is close to Old Oak Common, Birmingham Airport, through Birmingham International, and Manchester Airport; it will link in with HS3 going east-west; it will free up huge capacity for freight and metropolitan commuter services into all of those three major conurbations.
The right thing for this House to do is give emphatic support to this Bill today. We cannot keep pulling up by the roots big infrastructure projects when they are being half-built. If we do it with this one, no one will ever believe that we will do something as big as this as a country again.
That may well be the case, but we are now talking about hypotheticals, so I suggest that we wait until the review has finished and look at its conclusions in the context of the report from Allan Cook. The Government will make a decision at that time.
I turn to the comment of the noble Lord, Lord Birt, about why we do not have a long-term railway strategy. That is exactly what we are doing at the moment with the Williams rail review, which is looking at the status of the rail network and the service operators to see whether and how we can improve the system for the future.
I turn to some of the more specific points raised by noble Lords. There was a bit of discussion around investment in the north and how important it is; that was brought up by the noble Lord, Lord Wallace of Saltaire, and the noble Baroness, Lady Randerson. It is of course absolutely critical, as the Government recognise. Northern Powerhouse Rail could be transformative for the north, but probably not in isolation. It needs to be part of a larger project, which is why the Government are supporting Transport for the North to develop the options for Northern Powerhouse Rail. We committed £60 million at the spending review in 2015 and £37 million in 2018, which is on top of the £300 million we have committed to make sure that HS2 infrastructure accommodates a future Northern Powerhouse Rail and Midlands services. Therefore it is part of a bigger project, and other developments are certainly being included.
On the Oakervee review and accountability, I have already mentioned that costs, timescales and benefits will all be tied up in the review. The noble Lord, Lord Tunnicliffe, spoke about accountability and HS2. I refer him to a comment made by my colleague the Transport Secretary, who was very clear that he wanted us to be as transparent as possible. That includes on costs and schedule, which is why we published the Cook report. The noble Baroness, Lady Kramer, raised that as well. Therefore, there will be more transparency and accountability. We are not minded to introduce quarterly reporting on HS2 at the moment, as it already provides reports to Parliament, as required by the framework document, and we believe that that level is proportionate and sufficient. Of course, noble Lords may request debates on HS2 at any time.
The noble Lord, Lord Adonis, claimed that it was a bit left hand/right hand, given my opening remarks and the fact that we are having a review. However, I do not see it like that. The process for HS2 is positive, and the review we are having is a sensible reconsideration of the facts. A sensible reconsideration should never be confused for a lack of support.
A number of noble Lords mentioned whether work should continue during the Oakervee review. Certainly, the Prime Minister was very clear that the fact that we are having a review should not unnecessarily delay the progress of HS2. That would be wrong, and it would mean that costs would rise. That is why limited enabling works are being undertaken by HS2, and why your Lordships are being asked to consider phase—
Will the Minister at least acknowledge that the felling of trees and the damaging of ancient woodland when the matter is still under discussion would be a serious thing to do?