HS2: Cost

Lord Berkeley Excerpts
Wednesday 24th July 2019

(5 years, 4 months ago)

Lords Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Asked by
Lord Berkeley Portrait Lord Berkeley
- Hansard - -

To ask Her Majesty’s Government, further to reports that the cost of the High Speed 2 rail project will not be delivered within its current budget, what steps they are taking to ensure that the costs of that project remain within its budget.

Baroness Vere of Norbiton Portrait The Parliamentary Under-Secretary of State, Department for Transport (Baroness Vere of Norbiton) (Con)
- Hansard - - - Excerpts

My Lords, we do not comment on speculation. However, we will publish an updated business case by the end of 2019 based on the latest assessment of costs and schedule. We are clear that the project has a funding envelope set in 2015, and HS2 Ltd is in ongoing discussions with its suppliers.

Lord Berkeley Portrait Lord Berkeley (Lab)
- Hansard - -

I am grateful to the Minister. It is hardly speculation: in a letter, the new chair of HS2 says that the capital cost is likely to exceed £86 billion, not the £54 billion that the Minister spoke of. This has been confirmed by up to a dozen senior HS2 staff, who are tweeting—some of them have been sacked for their sins—that this figure is correct. This has been going on for three years. It is inconceivable that Ministers did not know about it, even before the HS2 phase 1 Bill received Royal Assent. I suggest that the Ministers have misled Parliament by not giving this new, higher figure that they have known about for three or four years.

Baroness Vere of Norbiton Portrait Baroness Vere of Norbiton
- Hansard - - - Excerpts

My Lords, the new chairman of HS2 has been in place for just over six months. He is undertaking a review of the costs and providing ongoing advice to government. This advice is not news; it is ongoing. We are working with him as he looks at all his supply chains to encourage him to ensure that the costs are appropriate. Various cost control actions are being undertaken at the moment regarding value engineering and challenging standards, and it is only right that they be given the opportunity to succeed. They also involve optimising commercial models with partnerships and challenging the requirements of the system.