Infrastructure Planning (Radioactive Waste Geological Disposal Facilities) Order 2015 Debate

Full Debate: Read Full Debate

Infrastructure Planning (Radioactive Waste Geological Disposal Facilities) Order 2015

Lord Avebury Excerpts
Wednesday 25th February 2015

(9 years, 2 months ago)

Grand Committee
Read Full debate Read Hansard Text
Lord Teverson Portrait Lord Teverson (LD)
- Hansard - - - Excerpts

My Lords, I am also not from Cumbria, although I shall have the pleasure of visiting Sellafield in two weeks’ time. I know that it consumes a vast proportion of the Minister’s budget in DECC, and I look forward to that visit.

My question is more one of logic. The Explanatory Memorandum states clearly, as does the legislation itself:

“This Order will bring certain development relating to geological disposal facilities for radioactive waste, and the deep borehole investigations necessary to determine the suitability of potential sites, within the nationally significant infrastructure project (NSIP)”.

I suppose that my question is this: whether one likes it or not—whether one is pro-nuclear or anti-nuclear—there is a certain logic to the idea that a radioactive waste disposal site would come within the decision-making of a major project. This was set up by the previous Government, as my noble friend Lady Miller has pointed out, and taken on by this one. It sort of fits within that. The exploratory deep borehole investigations seem to be a measure on a completely different scale, so I do not understand the logic of having both of those in. The exploration side seems logically to fit far more within the standard local authority planning system. I would be interested to hear a comment from my noble friend about why both these scales of project have been put into this order, rather than just one or the other.

While I am on my feet and we are on nuclear waste, at the beginning of this Parliament we looked at the national policy statement for nuclear power generation, and it has always slightly amused me that a footnote states:

“Geological disposal of higher activity waste from new nuclear power stations is currently programmed to be available from around 2130”,

some 115 years from now. I wondered whether the Government intended to keep their foot on the accelerator on that policy.

Lord Avebury Portrait Lord Avebury (LD)
- Hansard - -

My Lords, we seem to have overlooked that regular high-level nuclear waste is being generated at Sellafield already and plans have to be made for its safe storage and ultimate disposal. If plans go ahead to use the 140 tonnes of plutonium that have been stored up from previous nuclear programmes at Sellafield to generate electricity, as in the two proposals that have been put forward by CANDU and GE Hitachi respectively, there will be nuclear reactors on the Sellafield site using that plutonium and generating further waste. I suppose part of the Government’s thinking in having their eye on Cumbria is that this large quantity of nuclear waste has to be moved from the Sellafield site to the ultimate place of disposal. That concentrates their attention on Cumbria. However, when the noble Lord, Lord Liddle, said that he would like to see a survey of all the sites that might be suitable for this purpose, I was under the impression that a lot of work had already been done on the subject and that nobody had any thoughts of alternative sites that would be superior to Cumbria. I may be wrong and would be very interested to hear from the Minister whether that work has already been in train and, if so, what the results were.

Lord Judd Portrait Lord Judd
- Hansard - - - Excerpts

The noble Lord is right to say that work has previously been done and, having fairly carefully scrutinised it, it was far from clear to me that there was an absolutely decisive case in favour of Cumbria.

Lord Avebury Portrait Lord Avebury
- Hansard - -

This is what I am hoping we will hear more about from the Minister when she sums up: whether that work has been done or whether she agrees with the case that has been made for a national survey, which would obviously cause considerable delay.

That brings me to question of why this matter is urgent. Is it really necessary for a decision to be made now, for reasons that may be connected with the development of Sellafield, when we already have these additional reactors on the site, coupled with the existence of large quantities of high-level waste? Is it a matter of immediate necessity that we should have this GDF in the timescale that would be possible with the order and not without it? Suppose we were forced to wait for five years or so: would that have a catastrophic effect on how we dispose of the nuclear waste at Sellafield? Would lacking the GDF impose impossible or very difficult restrictions on the work that can be done at Sellafield because of the quantity of high-level waste that has to be stored there?

Other things being equal, obviously it is better for the GDF to be in the neighbourhood of Sellafield because the high-level waste has only to move a short distance and it avoids the necessity for rail facilities to move all this waste from Sellafield, where it is at the moment, to whatever alternative site is chosen. That would add enormously to the cost, I suppose, and is something we would like to avoid if possible.

--- Later in debate ---
Baroness Verma Portrait Baroness Verma
- Hansard - - - Excerpts

My Lords, as with all these things, we are talking about thousands of years. I am sure that as technologies evolve, those who have to take decisions thousands of years from now—it will not be me—will look at the decisions that we are taking now and consider whether our planning measures are as robust as they can be. Of course, new technologies and techniques will be developed that will change the sector. The nuclear industry itself will evolve, as will other technologies that will provide energy. However, we need to ensure that the decisions that we are taking now are being taken on the basis that we need a long-term solution to high-radioactivity waste, which needs to be put away safely so that it is secure and poses little danger to us all.

My noble friend Lady Miller asked about the Aarhus convention. The Planning Act 2008 provides for extensive levels of community engagement and public consultation but it also requires environmental assessments to be carried out at various stages of the planning process. Therefore, the Government believe that the process is compatible with the requirements of the convention and with associated European Union legislation.

My noble friend Lord Avebury and the noble Lord, Lord Judd, asked whether geological screening was being carried out. Radioactive Waste Management Ltd has begun the work, including engaging with interested stakeholders. It will produce draft screening guidance for public consultation. This, and the final screening results, will be reviewed by an independent group formed by the Geological Society of London. As stated in the 2014 White Paper, that will be carried out over the next two years.

I hope that I have managed to answer most of the questions. However, coming back to what we are discussing today, the Committee is simply being asked to consider the order, not to approve it. The Motion to approve will be tabled in the Chamber and noble Lords can oppose it then if they are strongly opposed to it. However, I suggest that if we are to make progress in finding a long-term solution to this significant national programme, we need to ensure that we provide the public with facts and not just bear in on myths that have been peddled over many years.

As the noble Baroness, Lady Worthington, pointed out, this debate needs to be properly informed. I would be happy—I am sure that the noble Baroness will welcome this—to widen that engagement and make the debate much more informed, so that people understand what we are trying to develop here.

Lord Avebury Portrait Lord Avebury
- Hansard - -

I hope that there is nothing in the order that precludes the decision being made including whatever Scotland decides it needs in the way of long-term facilities for the disposal of high-level nuclear waste. As the noble Baroness was asked earlier, surely we are not going to have GDSs in all the jurisdictions of the United Kingdom. I want an assurance that there is a facility within the ambit of the order for the Scots to come along to talk to us about what they are doing about long-term disposal, so that we do not have to have two separate facilities.

Baroness Verma Portrait Baroness Verma
- Hansard - - - Excerpts

My Lords, having obviously not satisfied noble Lords, if I undertake to write to them, that might be a better way forward.