Nationally Significant Infrastructure Projects and Local Road Networks Debate
Full Debate: Read Full DebateLilian Greenwood
Main Page: Lilian Greenwood (Labour - Nottingham South)Department Debates - View all Lilian Greenwood's debates with the Department for Transport
(1 day, 20 hours ago)
Commons ChamberI congratulate the hon. Member for Bicester and Woodstock (Calum Miller) on securing this debate, and I thank him for continuing to raise the issue of the London Road level crossing in his constituency. I recognise the concerns that he raises on behalf of local residents, and I appreciate the strength of those concerns—indeed, that was demonstrated by the presence of a number of his constituents today.
As the hon. Member is well aware, East West Rail launched a non-statutory consultation on 14 November on its proposals for the construction of a new railway that would provide a direct service between Oxford and Cambridge for the first time since the 1960s. That will provide billions in economic growth, which can be reinvested into the economy nationally. The upshot of that is that, as he says, East West Rail is proposing the closure of the London Road level crossing in Bicester. The possibility of that was noted in the non-statutory consultation that took place in 2021. I appreciate that for constituents facing these sorts of challenges it is difficult to have that uncertainty over a long period, when they know something is coming but it is some way off and they do not know exactly how it will impact on them.
The introduction of four East West Rail passenger trains per hour on top of existing passenger and freight services would represent—
I had forgotten that would happen at 7 pm.
The introduction of four East West Rail passenger trains per hour on top of existing passenger and freight services would represent a significant uplift in the rail traffic passing over the level crossing. On one level, that is a benefit, including to the hon. Gentleman’s constituents, who will have those new options for connectivity and the choices that brings in jobs, education or just getting about. That is a huge advantage not just to his area, but to the country. However, I understand that it does have less welcome impacts, and he has described the severance issue in his constituency in Bicester. Indeed, the hon. Member for Thornbury and Yate (Claire Young) and the hon. Member for Surrey Heath (Dr Pinkerton), who is not in his place, took the opportunity to highlight the importance of listening to the concerns of local communities when developing national infrastructure projects and working with them to mitigate any adverse impacts. I understand the importance of trying to do that.
Turning back to London Road and the level crossing, the level crossing barriers are currently closed for around 10 minutes every hour, but the closure time is expected to regularly exceed 32 minutes in the hour once all East West Rail services are operational, and the barriers could be closed for up to 12 and a half minutes of continuous downtime at a time. The impact of that would be queues half a mile long in either direction. That would have a huge impact not only on those stuck in the queue, but on air quality and broader congestion. It would cause the significant traffic disruption that the hon. Member for Bicester and Woodstock is rightly keen to avoid, creating long tailbacks, potentially through the centre of town, on a daily basis.
In addition to the traffic issues that would be caused by retention of the crossing, we also have to consider the personal safety of crossing users, whether they are crossing on foot, on bicycles or other non-motorised means. Analysis undertaken by the East West Railway Company determined that the risk of collision between a train and a road user, whether through misuse of the level crossing or an accident, was simply too high with the uplift in East West Rail services. We know that level crossings are a point of vulnerability on the rail network, and safety has to be a top priority.
In the view of the East West Railway Company and Network Rail, no further steps could be taken to improve the safety of the level crossing without undertaking its closure. I understand how disappointing that is to members of the hon. Gentleman’s local community. The East West Railway Company has reviewed all the possible options for the crossing, having consulted on them in 2021. Those options include a road bridge over the crossing and a road tunnel underneath it. As the East West Railway Company set out in its 2023 route upgrade announcement, providing an overbridge or an underpass presented insurmountable design, constructability and affordability challenges, and those options were not progressed.
I recognise, as the hon. Gentleman said, that when the area around the station was redeveloped, I think back in 2014, there might have been an opportunity to look at different ways the crossing could have been done, but at the time there was no East West Railway Company, and perhaps there was a lack of join-up that could have been provided at that time. However, I am afraid we are 10 years on from that.
The East West Railway Company did undertake to explore options to leave the road open to local traffic and develop options to retain connectivity for pedestrians, cyclists and other non-vehicle users, which would of course include mobility scooter users such as the constituent that the hon. Member referred to. Ensuring accessibility for those groups is extremely important.
Since 2023, the East West Railway Company has also considered providing new road bridges crossing the railway at other locations in Bicester. I am afraid that the modelling work undertaken on the downtime of the level crossing barriers produced the results that I set out for the extended closure period, so it is deemed not appropriate to retain the level crossing for local use only. Providing road bridges in other locations in Bicester has also been ruled out on the grounds of affordability and constructability. East West Rail has provided further details of its analysis that led to those conclusions in the technical report accompanying the current non-statutory consultation. I am sure that the hon. Member is aware of that, and that his constituents and those watching either will have read that or will now go and seek it out.
The options currently out for consultation of a pedestrian footbridge or underpass—they would of course be built to suitable accessibility standards to provide opportunities for cyclists and those using mobility scooters—alongside local road diversions, aim to provide the best possible balance between affordability and constructability and the needs of the local community in the hon. Member’s constituency. Both the footbridge and the underpass have been developed in the light of feedback received at and since the 2021 consultation. I assure him that there are opportunities for further design refinements to ensure that the solution meets the community’s need.
I note the hon. Member’s comments about the issues that he would like to see addressed and what he believes the majority of his constituents would prefer. I assure him that the Government are listening and that I and my colleague the Rail Minister will be happy to keep in touch with him. I am sure there will be opportunity for further discussion as things progress.
I very much appreciate the Minister’s fulsome response. There is one point that I want to press her on slightly. East West Rail’s own analysis has demonstrated that there is still a lot of technical work to be done—as I highlighted, some of the traffic modelling has not yet been done—so given that the information is not fully there and we have no public figure on how much money could be spent on a solution, will she accept that there should be openness to suggestions that might come from the community and not a closing down on the relatively limited range of options that East West Rail has so far provided? The Rail Minister gave me that assurance when I spoke to him, and I would be grateful if the Minister would confirm that there is openness to considering other options if they can be demonstrated to be technically and financially feasible.
I am happy to give the hon. Member that assurance, and I certainly would not disagree with the Rail Minister. I can also assure him that the proposed road diversions and any further enhancements required to minimise the impact of these diversions will be funded as part of the East West Rail project and that the local authority will not be expected to foot the bill. I have heard the representations about the importance of protecting the hon. Member’s constituents, and I know that my noble Friend Lord Hendy will have done as well.
I understand that having to travel to the centre of Bicester by an alternative route is unwelcome, but initial traffic modelling has demonstrated that any journey lengthening caused by vehicle traffic taking the alternative route proposed in the consultation will still be considerably shorter than the journey time extension caused by sitting in a traffic jam at the crossing for 10 minutes and upwards.
In closing, I signpost the ongoing consultation, and I invite all those with views, including the hon. Member’s constituents, to contact the East West Rail Company through the published channels before the closing date of 24 January 2025. It is so important that we listen to local people’s views and that we try to take them into account as we develop further mitigation. As I said, no final decision has been taken on which option to choose for the level crossing and future access for the local community. Feedback from the public will play a part in influencing the outcome. I would be pleased to keep in touch with the hon. Member as the position on the level crossing develops, and once again I congratulate him on securing this important debate, ensuring that his constituents’ concerns are heard in this place.
Question put and agreed to.