Keir Starmer Portrait Keir Starmer (Holborn and St Pancras) (Lab)
- Hansard - -

I obviously support the motion because it is important for my constituents to have the chance to petition the Select Committee. That does not, however, mean that I support the proposals or HS2. I oppose HS2 on cost and on merit: it will not achieve its stated objectives.

The impact of HS2 on my constituency—on residents, businesses and the environment—will be devastating. It is a major cause of concern to very many of my constituents. Such is the concern throughout the constituency that it is raised with me daily. The plans for changes at Euston station have a long and sorry history. Standing back, we can see that not the least reason for that is that it does not make sense to bring a 21st-century, high-speed railway into a densely populated part of north London simply because that is where the conventional station is.

Robert Goodwill Portrait Mr Goodwill
- Hansard - - - Excerpts

There was a lot of disruption for the constituents of the hon. and learned Member—or for the people who are now his constituents—when the work was done at King’s Cross station. Do they consider that the work was worthwhile, now that the station has been finished?

Keir Starmer Portrait Keir Starmer
- Hansard - -

That is a false comparison, as I am sure the Minister knows. The situation in and around King’s Cross cannot be compared with the densely populated area around Euston. We only need to look at a map, as I am sure the Minister knows, to see that the situations are not comparable. In fairness and in respect to my constituents, it is not right to make such a point when, anxious about their situation, they are coming to me daily. When I address them at meetings, I can see the anxiety on their faces. Please let us address the motion with respect to them, not make false comparisons. The Minister knows that the two situations are simply not comparable.

We have had plans, amended plans and further amended plans for Euston, but the only sensible plan is to abandon the project altogether. Far from being an improvement on the other plans, this plan is the worst of the lot. It leaves my constituents with all the pain and none of the gain. I want to focus particularly on the phased approach.

The plan offers and sets up decades of blight with no assurance about when the project as a whole will be finished. I will spell that out, because this is what it means for my constituents. Phase 1 will take up to 2026 and phase 2 will then go up to 2033, while the development of the eastern side of the station has no start or finish date. That amounts to 16 to 20-plus years of works and blight, so we can see why my constituents are coming to me daily and why they are so concerned.

Under the proposal, we will have half a station, but it will take twice the time. I will have children born in my constituency who will grow up and probably leave school knowing nothing other than construction works at what is likely to be the biggest construction site in Europe. I have people at the other end of the scale who will retire in the next few years and probably spend their entire retirement with the construction works going on. That is what this plan means for many thousands of people in the Euston area.

The Secretary of State described the plans in one document as

“essential for the local community”.

That beggars belief and is testimony to the failure of HS2 and others to listen to what the local community is saying.

I pose the following questions for the Minister. First, the hybrid Bill was premised on a new station being delivered at Euston by 2026. What is now proposed is half a station by 2033. How did HS2 Ltd get its planning so hopelessly wrong that we are in that situation? Secondly, why is HS2 Ltd no longer able to build a new station at Euston by 2026? Is it the cost, the impact on existing users or some other reason?

Thirdly, and I would like some detail on this, what is the current budget for the new station at Euston? How do the current costs compare with the estimated costs in March 2010, when the route for phase 1 was announced, and November 2013, when the hybrid Bill was deposited in Parliament?

Fourthly, the extended construction completion time of 2033 and beyond will blight the lives of up to 17,000 people in my constituency who live within 300 metres of the construction work. What is the proposal to compensate them for that?

Fifthly, appendix A to the explanatory note before the House states that

“The development principles in the EAP include promoting ‘comprehensive, commercial-led, mixed-use development above and around the new and existing stations’.”

That is at odds with the No. 1 objective in the Euston area plan:

“Prioritising local people’s needs: To ensure that new development meets local needs by ensuring homes, jobs, businesses, schools, community facilities and open space lost or affected by HS2, should it go ahead, are reprovided in the Euston area.”

I ask for an assurance from the Minister and, if appropriate, the Secretary of State that they recommit to that No. 1 objective in respect of local needs. Sixthly, by what date will the Government commit to re-provide new social housing, open spaces and community facilities on the land acquired for the new station?

My constituents are entitled to answers to those questions. The plan for Euston is a mess and there is a lack of information in the provisions. HS2, Network Rail and Transport for London need to step up and listen to local residents and businesses, who speak with a clear voice in opposition to these plans.