South West Rail Resilience Programme Debate

Full Debate: Read Full Debate
Department: Department for Transport

South West Rail Resilience Programme

Lord Swire Excerpts
Monday 22nd May 2023

(11 months, 1 week ago)

Lords Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Baroness Vere of Norbiton Portrait The Parliamentary Under-Secretary of State, Department for Transport (Baroness Vere of Norbiton) (Con)
- Hansard - - - Excerpts

My Lords, I can confirm that Network Rail has delivered two phases of the south-west resilience programme, providing protection to the railway at Dawlish from coastal flooding. The third and fourth phases addressing cliff protection measures are in delivery, with a combined budget of £85 million. Network Rail is being funding to deliver a detailed proposal for the fifth and final phase, which addresses cliff protection for a mile-long stretch of the railway.

Lord Swire Portrait Lord Swire (Con)
- Hansard - -

My Lords, we listen with some amazement—

None Portrait Noble Lords
- Hansard -

Order!

Baroness Vere of Norbiton Portrait Baroness Vere of Norbiton (Con)
- Hansard - - - Excerpts

As I mentioned in my opening Answer, Network Rail is working on the fifth phase of the works in some detail; we need to establish detailed proposals for this mile-long stretch of the railway. Local consultations have happened, and there was some reluctance around some of the proposals put forward. Therefore, Network Rail is looking at the scope and costs of the fifth phase.

Lord Swire Portrait Lord Swire (Con)
- Hansard - -

My Lords, I apologise for being a bit too quick, which is more than you can say for any of the trains travelling to the south-west. In the south-west, we look and listen in envy to talk of chopping off bits of time on the cross-Pennine railway and others. That is not a luxury we have; we have only one railway beyond Exeter linking the whole south-west peninsula. If Dawlish goes down, we have no connectivity at all. While I very much welcome all the money and the moves the Government have made with the resilience surrounding Dawlish itself, until such time as we have a second railway bypassing or connecting Plymouth—either west of Dartmoor or in line with some of the other options—we can never be sure that we can keep the south-west connected 365 days a year.

Baroness Vere of Norbiton Portrait Baroness Vere of Norbiton (Con)
- Hansard - - - Excerpts

I welcome my noble friend’s interest in this Question; I know that he raised this issue in the other place many times. I assure him that delays on the line as it currently stands are significantly down, from 53.6 minutes per 1,000 services in 2018-19 to just 36.1 minutes per 1,000 services in 2022-23, so it is important to note that the resilience of the line is improving. The department has looked at alternatives—additional routes through to the south-west that might provide additional resilience. However, we are focused on improving the resilience of the line as it currently stands. In proposals for restoring elements of railway that previously existed, the case was not set out sufficiently.