(5 years, 10 months ago)
Westminster HallWestminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.
Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.
This information is provided by Parallel Parliament and does not comprise part of the offical record
As the hon. Gentleman will know, the fact that the extra £1 billion was put in place was particularly due to the pressure applied by my hon. Friends the Members for Congleton and for Eddisbury. As I only returned to the House at the 2017 election, I too applied pressure, because I think it is vital that schools get the money they need for education. For me, education is one of the key building blocks of social mobility that every child needs, so I did indeed make sure that we pressed for further funding. I would like that to be on the record.
Does my right hon. Friend agree that the pressure that was put on by my hon. Friend the Member for Congleton and myself, and indeed by other hon. Members who met with the Minister to ensure that a minimum level of funding was applied, resulted from the particular problems in Cheshire East and Cheshire West and Chester? Does she also agree that those problems are linked to the formula by which rurality is calculated, which is as the crow flies, rather than as the car or bus travels?
(7 years, 3 months ago)
Westminster HallWestminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.
Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.
This information is provided by Parallel Parliament and does not comprise part of the offical record
One key aspect of the business case for HS2 involved consideration of the economic benefits that it could bring. I question whether the economic blight associated with it has been appropriately considered. It appears very often that, in effect, a line has been drawn on a map and only afterwards have the problems caused by that line been adequately identified. My hon. Friend gives a very good example of how the construction impacts are not being adequately thought about at this stage.
For the reasons that I have set out, I urge HS2 and the Minister to act early in relation to Wimboldsley, where there are clearly significant issues, and to move the rolling stock depot to a more suitable site, either its original proposed site at Golborne or a new location, such as Basford sidings, south of Crewe.
I also wish to raise the decision last year to realign the route through Eddisbury 800 metres to the west, and the concerns that have been raised about taking it through an area with a greater amount of wet rockhead—unstable ground liable to subsidence as a result of salt. HS2’s decision to move the route came about because the original 2013 proposed route went through the area where the UK’s strategic gas reserves are stored. It was of course practical to move the route away from the gas reserves, but moving it 800 metres to the west has caused other problems, because it still goes through an area with geotechnical challenges that are not easy to engineer around and where there will be a significant cost to the communities and the taxpayer.
TerraConsult Ltd produced an independent geotechnical report on the proposed change of route and concluded that there would be an increase of 11% in the route length over wet rockhead. HS2’s lead ground engineer has called the ground conditions in the Cheshire salt area “spicy”, referring to the engineering challenges of building a high-speed railway line in that area, and HS2’s own consultant, Wardell Armstrong, recognises the risks of building HS2 through Eddisbury in its report on salt-related ground instability.
The Government must recognise the risks in the area and move the route away entirely. Alarmingly, before making route choice proposals, HS2 had not done any detailed ground surveys for use as a baseline to track ground movement. As far as I am aware, those surveys have still not been carried out.
The engineering challenges require significantly increased height and length of the embankments and viaducts—up to 26 metres. There will be two additional crossings of the Trent and Mersey canal, one at the location of previous subsidence at Billinge. That comes at an estimated additional cost to the taxpayer of £750 million and significantly increases the noise and visual damage for communities.
The route alternatives set out in the TerraConsult report should be looked at and given serious consideration. The decision document issued in July, following the recent consultation, does not contain any reference to the TerraConsult report or the points made in it. Was it considered in detail before a decision on the route in Eddisbury was made? If it was, why has HS2 to date failed to disclose the AECOM report, to which the Minister has referred in correspondence, despite numerous requests to do so?
In raising such serious issues, I consider the impact on Eddisbury and my constituents first and foremost, which brings me on to community engagement and the levels of communication and transparency. Progress has been made with the appointment of a new director of community engagement last December, and the publication of a residents’ charter, but information on the route has been difficult to obtain and public meetings have often left local residents unsatisfied.
When my office has requested information from HS2, there has often been a lengthy delay in responding. Previously, I have had to resort to freedom of information requests. When information is provided, it often lacks the necessary detail and does not fully answer the request. For a significant government project with huge ramifications for the public, all that must improve so that genuine local concerns can be fed into the process adequately.
I congratulate my hon. Friend and neighbour on securing this important debate. I endorse all the points that she is making, in particular those about safety, security, suitability and cost. My constituency, too, is full of brine fields and wells where salt has dissolved and been pumped out, which creates craters underground. Ros Todhunter, a geologist who lives in Lostock Green in my constituency, has also discussed land movement. Railway engineers talk about permitted movement of 5 mm, but we could be looking at 0.5 metres. As my hon. Friend has said, there should be discussions with people who know the land well—their families have farmed this land for hundreds of years and they know about problems under the earth that, I am afraid, the Government have so far not looked into.
I am grateful for my right hon. Friend’s intervention, because I have met Ros Todhunter and am aware that Ministers and HS2 have had high-level technical reports from her explaining some of the real difficulties in my right hon. Friend’s constituency and mine. A deep worry is that HS2 does not seem to be disclosing the appropriate level of technical reports to experts who are meant to be giving expert opinion highlighting proper concerns which are right to express at this stage in advance of a serious engineering project. One such expert is one of the most eminent professors in the field of salt subsidence, who wrote to the Secretary of State more than 18 months ago to emphasise that ground-level surveys ought to be started now, so that HS2 can identify subsidence and problem areas.
I say to the Minister that it would be extremely beneficial for MPs across the House who are affected by HS2 to be regularly updated by the engineering team on the detailed design of the route, to ensure that there is an appropriate level of scrutiny and to allow valuable input in the process. Reports regarding route decisions and sift documents ought to be shared with Members as a matter of course, not kept from us. There simply has to be better engagement, and with an acute awareness and understanding of local issues.
Many constituents have raised legitimate concerns about the compensation schemes for properties that lose value due to their close proximity to the route. Those schemes are failing to recognise the true extent of the blight caused by HS2, and more needs to be done for residents. A number of tenants have particular problems and, as it stands, do not stand to be compensated at all—particularly tenants with agricultural holding tenancies and a tenant in a property owned by a charitable trust, who has a secure tenancy and may not be able to secure another similar to the one that he has now.
There appears to be an increasing trend in phase 2b of need-to-sell applications being turned down. The latest figures show that, out of 139 applications received, just 25 have been accepted, with 49 rejected and 52 pending. Those living beyond 120 metres from the line have no alternative but to rely on the restrictive need-to-sell scheme. I am seeing an increasing number of cases in which constituents are unable to sell their homes due to HS2 but are not fulfilling the highly subjective and restrictive compelling-reason-to-sell criteria. They are then trapped and unable to move, which is extremely unfair. That really needs to be looked at again, with further consideration given to a want-to-sell scheme for those who are blighted and cannot sell. More also needs to be done for tenants who are affected.
On a more general note, I raise the issue of the destruction of woodland in phase 2b. The Woodland Trust estimates that phase 2b alone will destroy or damage at least 18 ancient woods. HS2 must be seen in the context of being a project for the future, but the current mapping along the whole route sees 98 irreplaceable ancient woodlands affected. I urge the Department for Transport to do all it can to diminish the impact on rural areas and to promote a green agenda.
I urge the Minister to reconsider the route of phase 2b through Eddisbury. It would be much more sensible to craft constructive solutions to the issues I have outlined. The new proposed location for the western leg rolling stock depot is extremely unsuitable and will cause long-lasting damage to the local area. The 2016 route realignment through Cheshire raises serious environmental, noise and safety risks and cost implications, as highlighted in an independent geotechnical engineering report, and should be looked at again.
Finally, I hope that if we shine a spotlight on examples of poor engagement and a lack of transparency thus far by HS2, the Department for Transport will look at ways of improving collaboration with communities and local MPs who know and understand their areas. Then, not only will local aspects be fully taken into account, but public trust in the project will improve.