Tuesday 13th May 2025

(1 day, 9 hours ago)

Public Bill Committees
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Matthew Pennycook Portrait Matthew Pennycook
- Hansard - - - Excerpts

The purpose of clause 37 is to remove the need for Transport and Works Act order applicants to apply to multiple consenting authorities for separate authorisation requirements under relevant heritage regimes in England and Wales, such as listed buildings and scheduled monument consents. Instead, the clause provides for the consolidation of the application process for certain heritage authorisations, so that they can be obtained through the Transport and Works Act itself. I must make clear that it is for applicants to determine whether they want to proceed on the basis of existing arrangements, namely consulting multiple consenting authorities, or whether they want to obtain those consents through the Transport and Works Act itself, in which instance the Secretary of State for Transport would need to confirm that that could be undertaken via that route. The consents would be obtained as part of the TWA order process and the decision-making process that pertains to it.

In making this change, as with other changes that we have made in this part of the Bill, we would bring the Transport and Works Act order process in line with the Planning Act 2008, which provides a one-stop shop development consent order process for major infrastructure. To ensure proper oversight is maintained throughout the amended process, applicants will still need to consult the relevant consenting authorities before applying. I commend this clause to the Committee.

Schedule 2 amends the Ancient Monuments and Archaeological Areas Act 1979 and the Planning (Listed Buildings and Conservation Areas) Act 1990 as a result of the changes made by clause 37 of the Bill. As I have just set out, clause 37 enables an order under the Transport and Works Act to obtain certain consents through the Act itself, rather than requiring separate applications to each relevant consenting authority. Schedule 2 disapplies offences that would otherwise arise from proceeding without those consents or authorisations. The inclusion of this power is a prudent, practical and reasonable step to take to ensure the most efficient legal framework moving forward. I commend the schedule to the Committee.

David Simmonds Portrait David Simmonds (Ruislip, Northwood and Pinner) (Con)
- Hansard - -

It is a pleasure to serve under your chairmanship, Ms Jardine. The Opposition broadly understand the direction of travel that the Minister has set out and the principles underlying it are clearly quite sensible.

Will the Minister give us a degree of assurance, particularly about the process for determining the circumstances in which the authorities that are listed and the circumstances that are listed may be set aside? That is significant because significant infrastructure developments are often close to heritage railway buildings and historic sites where there will be a legitimate expectation from both local authorities and residents that a proper consultation will be undertaken.

We know that, in the past, the effect of that regime has been that in many cases developers, in places such as Royal Quay in my own constituency in Harefield, have chosen to put historic buildings back into use for a new purpose. For example, formerly industrial buildings connected with Victorian transport networks could be used for residential development, rather than simply demolishing and clearing the sites and losing that heritage asset in the process.

It would be helpful to understand how we will ensure, through the regime as set out, that those considerations are fully taken into account. I appreciate that we will debate the green belt later on, but there is significant interaction in the Bill between the different types of regime that apply, and we have already had much debate about the green belt and the grey belt.

I am aware that the Secretary of State for Housing, Communities and Local Government yesterday issued a decision with respect to a site just north of London, and the effect of her determination is that any land on a transport corridor located between, for example, a motorway and a village, even if it is currently in the green belt, will be considered to be grey belt for the purposes of developability. That will clearly have a significant impact in similar situations in locations with a significant heritage element that are close to railways, motorways and other such transport networks that would potentially, from a developer point of view, benefit from swifter development without a consultation being undertaken. However, from the perspective of local residents and the wider community concerned about heritage and land use, they are losing the opportunity to have this.

Gideon Amos Portrait Gideon Amos (Taunton and Wellington) (LD)
- Hansard - - - Excerpts

I rise to speak either against the clause or in favour of amendment 7, which is in my name. I am not sure which, but I am sure you can advise me, Ms Jardine. We have significant concerns about the clause, and I will spend a few minutes on them as it is, perhaps, more serious than it first appears. The clause would disapply the need for listed building consent, conservation area consent, scheduled ancient monument consent and notices for works on land of archaeological importance from Transport and Works Act projects.

Our heritage has benefitted from protection under criminal law since Lord Avebury in the Liberal Government brought in the Ancient Monuments Protection Act in 1882. The Act provides that anyone who damages a monument commits an offence punishable by imprisonment

“with or without hard labour for any term not exceeding one month”.

That protection, and much of the wording in that Act, has survived, and the relevant wording remains in the main and principle Acts for listed buildings: the Planning (Listed Buildings and Conservation Areas) Act 1990 and the Ancient Monuments and Archaeological Areas Act 1979. My suggestion is that this is not the time to remove such strong statutory protection and criminal sanction from measures to protect ancient monuments and listed buildings.

I appreciate that the Government, in their memorandum to the Delegated Powers and Regulatory Reform Committee, say that the approach is similar, but not as wide as the Planning Act 2008 approach, which the Minister has mentioned, and I fully understand the single consenting regime objective. It would be narrower in some ways because, in the proposed Transport and Works Act approach, it could be possible to be more selective about which measures are disapplied. However, the Planning Act 2008 approach is very different, because regulations made under it enshrine those same legal tests that go back decades—and, in some cases, centuries—so that they remain on the statute book and applicants under that Act still must comply with them.

If our country’s heritage is worthy of protection under criminal law, as the Liberal Democrats believe that it is, the same tests should surely be applied under the Transport and Works Act as under other legislation. Those are long-standing tests. In relation to listed buildings, the wording that many in the sector will know is that we must have

“special regard to the desirability of preserving the building or its setting or any features of special architectural or historic interest”.

Those words ring down the years. For scheduled ancient monuments, the requirement was to have regard to the “desirability of preserving” the scheduled monument or its setting and, in conservation areas,

“to the desirability of preserving or enhancing the character or appearance of that area.”

Those are familiar words that, as I say, ring through legislation over many years. They should not be removed from the Transport and Works Act process altogether, which this clause would do. These are central principles of heritage protection that have lasted decades, if not centuries. The Government may point out that, as they say in the explanatory notes, section 12(3A) of the Planning (Listed Buildings and Conservation Areas) Act 1990 remains in place, which provides:

“An application for listed building consent shall, without any direction by the Secretary of State, be referred to the Secretary of State instead of being dealt with by the local planning authority in any case where the consent is required”.

Although that section is referred to, it does not apply here, because consent is not required. All the requirements for consent are disapplied by the clause in this Bill, so there would be no recourse to consent under that route.

Our recommendation is that the important statutory tests be repeated in the legislation for Transport and Works Act projects, just as they are for all other projects, including in regulations made under the Planning Act 2008.

Many heritage organisations share our concerns. The National Trust says:

“We have serious concerns regarding the scope of Clause 37 of the Bill which seeks to disapply existing heritage regimes. This clause enables Transport and Works Act 1992 orders to disapply authorisation”

for listed buildings, and so on. It continues,

“we have strong concerns about the possible disapplication of heritage regimes for transport infrastructure developments. There is a risk that this could enable harm to heritage assets without proper scrutiny and go further than the stated ambition of the Bill.”

The Heritage Alliance has stated:

“Until greater clarity and detail is forthcoming from government, we continue to have significant concerns regarding its potential to cause…unintended harm to heritage assets.”

Even the Government’s own agency, Historic England has said:

“Whilst the clause provides discretionary powers for the Secretary of State on whether to disapply the legislative provisions relating to heritage, as drafted there is a lack of clarity as to how and when this discretion would be applied. This risks resulting in uncertainty and inconsistency, which would undermine the policy intention…In addition, the disapplication of the legislative provisions for heritage does not provide any equivalent safeguards for the protection of heritage in relation to the authorisation and enforcement provisions for listed buildings and scheduled monuments, as exists at present”

in legislation. It goes on:

“The clause, as currently proposed, would therefore result in a weakening of heritage protection.”

It concludes that

“the current wording of Clause 37 may not actually deliver the policy intention of streamlining planning decisions, whilst having the unintended consequence of reducing heritage protection.”

In short, we are very concerned about the removal of such long-standing legal protections for our heritage. In our view, they must be put back on the statute book in one way or another.

--- Later in debate ---
David Simmonds Portrait David Simmonds
- Hansard - -

I know that my hon. Friend the Member for Hamble Valley wants to raise some points, but I want to ask a couple of slightly technical questions.

The first relates to clause 44(6), on directions in relation to planning fees. The publication of a schedule of planning fees is part of the statutory council tax-fixing process, which every local authority is required to undertake. As we hear from our residents, that generally takes place in February and comes into effect at the start of the following financial year. If a local authority publishes its proposals, as the Minister described in respect of cost recovery, it needs to be confident that any change—in the form of a direction from the Secretary of State—will come in a timely manner that enables further consultation so that the lawful council tax fixing can occur. What provisions will be in place to ensure that any objection from the Secretary of State will come in a timely manner?

My second slightly technical question is this. My experience of planning authorities is that there is huge variation in their cost bases. That partly reflects a shortage of staff, but it also reflects different local arrangements. An authority with large numbers of householder applications may use an outsourced service to process them at a relatively low cost. However, if senior, experienced, in-house planning officers are responsible for managing all planning applications, that will significantly increase the cost. Neither of those things is illegitimate; each is a manifestation of the democratic decision making of elected politicians about what is appropriate for their community.

It would be helpful to understand what process the Secretary of State will go through in determining what a reasonable level of planning fees is. For example, will she consider the requirement for specialist input at a technical level because there is a significant amount of radon gas, which is found in certain challenging sites because of their topographical nature? Whether there is a requirement for remediation and specialist consultancy will be critical to a proper assessment of that planning application. Other local authorities may have development opportunities of a different nature. Will the Minister set out his thinking on that? That would be enormously helpful.

Rachel Taylor Portrait Rachel Taylor
- Hansard - - - Excerpts

When the Committee met the witnesses a week or so ago, we touched on section 106 agreements and the role of planning authority lawyers in that process. I think that the fees for processing and determining applications include the process for agreeing a section 106 agreement. Is it the Government’s intention to include costs arising from the legal department’s time and efforts in determining those applications in the ringfenced planning application fees? I am aware that there is a severe shortage of qualified and experienced property lawyers in both local authorities in my constituency, as well as a shortage of planning officers.

--- Later in debate ---
Matthew Pennycook Portrait Matthew Pennycook
- Hansard - - - Excerpts

That is an interesting point. That would be a fairly extreme measure for a local authority to undertake but, if I have understood the hon. Gentleman correctly, it could drain its planning department budget, foreseeing that it would be able to set a fee at an appropriate rate to make up for that, and therefore in a sense evading the clear stipulation that we have here to ringfence planning fee charges to the provision of planning services. I will say a couple of things on that basis.

As I said, local planning authorities will have to consult publicly and test their fee level. As part of that, they will have to consider the benchmarking exercise that we will undertake for the default national rate—so we will have a sense of what different local authorities are charging. However, if the hon. Gentleman will allow me, I shall go away to reflect more fully on how—as I hope is clear we have been thinking today—local authorities without the best intentions might seek to game the system.

Matthew Pennycook Portrait Matthew Pennycook
- Hansard - - - Excerpts

The final point I will make before giving way is that, were a local authority to seek to evade that ringfencing provision by reducing the amount of resource going into its planning department—a not particularly sensible route to take—and then, potentially, it were not able or allowed to charge a fair and proportionate fee set in that regard, it would come under the usual planning performance dashboard, where the Department can look at the local authority for not providing a timely service or performing appropriately. As the hon. Gentleman knows, a set of intervention powers would be available to national Government, were that the case.

It is far more likely, however, as we have heard from local authorities, that they would use the power to set local fees that reflect the cost of services, using it to bring more resource in and—generally, this is what they want to do—to start processing applications in a more timely manner than they can now.

David Simmonds Portrait David Simmonds
- Hansard - -

The Minister’s response has been excellent. Clearly, there will be a number of different arrangements at a local level. That should encourage us, as a Committee considering the legislation, to reflect a little further.

In the example that the Minister talked about—the behaviour of local authorities—it may not be about those who have ill intentions. Some local authorities may have a planning and building control department—although the two regimes are separate, there is great commonality of skills—while others may have outsourced one or both those functions, or have them in-house but entirely separate.

As part of the published council tax fixing, there is a requirement to set out a schedule of fees for building control. Some local authorities may choose to bundle that together, so when people put in a planning application, they pay for both; but others may do that separately. Some developers, including householders, may choose to purchase the building control privately, even though they could purchase it from the local authority. A lot of factors will determine what a reasonable cost base is. It would help if the Minister shared with the Committee some further thinking on how the Government might seek to establish a baseline, in particular in the light of potential challenges in the future by developers who feel that the level of cost at a particular spot is other than reasonable.

I press the Minister a little on how that interacts with two further points that he made. Government new clause 39 refers to the power of the Secretary of State to implement a surcharge as a percentage of a planning fee that has been set. From what I understand of what the Minister said in his commentary, that will principally be to fund the work of the statutory consultees. Clearly, the imposition of a surcharge will then form part of the planning fees that have to be part of the statutory consultation on the legislatively fixed timetable that the local authority has to follow. How will the Government ensure that that timetable is respected, so that they themselves are not subject to the challenge?

Matthew Pennycook Portrait Matthew Pennycook
- Hansard - - - Excerpts

I thank the hon. Gentleman for pressing those two points. I am more than happy to come back to the issue in more detail, but as a general point, a lot of further detail is yet to come post consultation and the regulations’ being laid. We will provide further detail then on some of the technical questions as to how the power will be implemented.

The surcharge introduced by Government new clause 39 will provide the ability to fund the statutory consultees and other bodies that provide assistance and advice in relation to the planning application process. For example, we may wish to fund training and guidance for local planning authorities so that they can better engage with statutory consultees. However, the surcharge, which, as he rightly says, comes as an additional amount on top of the fees for processing applications, is very much intended to address the particular challenges that we are facing in terms of how statutory consultees are able to engage with the process in a timely manner, so that we get that advice up front.

--- Later in debate ---
David Simmonds Portrait David Simmonds
- Hansard - -

May I press the Minister a little further? That is a really helpful answer in illuminating the Government’s thinking, but could he explain to the Committee how that will interact with the existing arrangements for planning performance agreements, which are very common in respect of larger-scale planning applications? Clearly, if a developer required to engage with all this wider statutory-consultee process is already entering into a voluntary agreement with the local authority to fund the process, there is a risk that that will have an impact. It risks either reducing the ability of the local authority, because that surcharge is effectively being taken by the Secretary of State, or increasing the cost base and therefore opening up the question whether the planning fees are reasonable in the first place.

Matthew Pennycook Portrait Matthew Pennycook
- Hansard - - - Excerpts

I would say two things in response to that, and then perhaps, Ms Jardine, in the interests of making progress on the Bill, I will happily write to the Committee to set out further details of the operation of the surcharge.

First, on how the surcharge will be processed and distributed, it will, as the hon. Gentleman rightly says, be paid by the person collecting the fee to the Secretary of State in a manner and at a time prescribed by regulations, which are forthcoming. Outside the regulations, the proceeds will then be earmarked for distribution to bodies that provide advice and assistance in the planning process, including by way of consultation responses.

Secondly, the question has been asked several times whether the Government have properly considered the cumulative impact of fees and charges—are we getting the fees right? We are very aware that the surcharge will increase the fees that are already out there—it is an additional levy in that sense—and that other measures in the Bill may already result in fee increases. I repeat that we are committed to consulting on the proposed rates and the type of application that this should apply to—not least to allow the development sector to fully engage with those proposals.

On that basis, I think it would help the Committee if I set out later—chapter and verse—how we think both the clause and the surcharge will operate, on a very practical basis, and how local authorities can understand the Government’s intent in bringing them forward.

Question put and agreed to.

Clause 44 accordingly ordered to stand part of the Bill.

Clause 45

Training for local planning authorities in England

--- Later in debate ---
David Simmonds Portrait David Simmonds
- Hansard - -

I am struck by the Minister’s point about the need for consistency. We will all be conscious of the level of inconsistency in delegated planning decisions, which make up around 95% of decisions on planning applications. Does he have a programme in mind to achieve the level of consistency for those decisions that this measure will bring to decisions made by democratically elected members?

Matthew Pennycook Portrait Matthew Pennycook
- Hansard - - - Excerpts

If I could probe the hon. Gentleman in turn, does he mean consistency in the decisions made by expert planning officers rather than on individual planning applications?

David Simmonds Portrait David Simmonds
- Hansard - -

Actually, the answer is both. We will all know of people’s experience with local authorities: they meet a planning officer to discuss a delegated planning decision and they receive advice, but when it is submitted, it is considered by a different planning officer who takes a completely different view. Given that that is how the vast bulk of planning applications are dealt with, if the Government’s aim is to bring consistency and certainty to the process—it is a laudable aim—it will be necessary to focus on the more than 90% of decisions that are already made under delegated powers, as well as this measure, which is for that small number considered by the planning committee.

Matthew Pennycook Portrait Matthew Pennycook
- Hansard - - - Excerpts

That is a fair and reasonable point. If the hon. Gentleman will allow me, I will write to him to set out the Government’s thinking on that issue. If it is available—I fully expect that it will be— I will give him some sense of the level of refusals on appeal for decisions made by committees versus decisions made by expert planning officers, which I think would be relevant. In general terms, in many instances, we think that expert planning officers have the relevant expertise to make good decisions on the basis of planning law. We are trying to ensure through this clause that elected members also have that experience in place through mandatory training.

As has been rightly said, the clause is about building on existing good practice—there is very good practice out there—and ensuring that it is implemented consistently across the country. It is worth noting that mandatory training for committees was strongly supported by the sector as a whole in the responses to the planning reform working paper where we set out ideas in this space, lots of which we are taking forward.

We will introduce regulations to specify which planning functions are covered by this measure, what the training looks like—its nature and content, and how it will be delivered—and details about the certification process. Those regulations will be subject to further engagement with the sector and I will reflect on all the points that have been made today.

--- Later in debate ---
Nesil Caliskan Portrait Nesil Caliskan
- Hansard - - - Excerpts

I recognise a number of those points, but supply of housing is the fundamental reason why we have a housing crisis in this country. The amendments being proposed sit alongside many of the solutions that she is seeking. Without our ability as a country, including local authorities, to see housing delivered at the necessary speed, we will never see the number of affordable homes we need or a buy-to-let market being constrained in the way that it needs to be. Supply is the No. 1 reason why we are experiencing a housing crisis. We cannot deliver the number of homes we need without fundamentally looking at the planning system.

Finally, on councillors having their say, the idea that councillors run for public office only because they want to sit on a planning committee—it sounded as if a number of Members were insinuating that—is, I am afraid, a little out of touch. There are lots of ways in which local authorities and councillors can make a difference. Planning committees are indeed one of the most attractive committees, but there are multiple layers of regulatory policy in a local authority that members not only can have a say on, but get to vote on. Earlier, I referenced a local plan that full councils are required to vote on.

An officer making a decision on an application that will not go to a planning committee does not remove a local authority’s ability to put out for consultation. Members of the public, and indeed councillors, will still have the opportunity to submit their views through what will be a statutory consultation period. Local authorities and planning officers will be obliged to take those views into consideration.

I want to underline the point that if we accept that there is a housing crisis in this country and that the planning system is broken, surely planning has to be an aspect that we look at in recognition that local authorities are sometimes being hindered by the existing framework. The speed at which we can deliver housing through a more streamlined planning system, putting faith in professionals in a local authority alongside councillors, will allow us to deliver the 1.5 million homes that we so desperately need.

David Simmonds Portrait David Simmonds
- Hansard - -

I will start where the hon. Member for Barking finished. We know that the planning system has delivered consents for 1.5 million new homes in England, where the development sector has failed to step up. One of the things much debated among political parties is the fact that that seems to suggest that, although there are undoubtedly issues, the planning system has been good at producing the opportunity for those new homes—the challenge has been the inability of the development sector to step up to the plate. That should be the priority to address.

My hon. Friend the Member for Hamble Valley mentioned the Mayor of London’s recent decision about going into the green belt. That is in the context of a capital city that already has 300,000 unbuilt planning permissions for new homes. The Opposition’s argument is that the priority should not be increasing the stock of unbuilt planning permissions but delivering the homes that our country needs.

Gideon Amos Portrait Gideon Amos
- Hansard - - - Excerpts

As an illustration of the hon. Gentleman’s point about unbuilt planning permissions, in Somerset there are permissions for 11,000 new homes that have not been built, while the new NPPF requires a 41% increase in the allocation of permissions. There is no record of these pressures having led to an increase in the number of houses actually being built.

David Simmonds Portrait David Simmonds
- Hansard - -

If we look at the statistics from the ONS on new household formation and the balance between that and the delivery of new homes, we see that they are reasonably in balance at the moment. We know that many people would like a bigger home or a different type of home, and that is why we have consistently argued that we need to focus on the nature of the homes we are delivering, not just on the units being delivered through the planning system.

Members have consistently made the point about centralisation. The UK is already an exceptionally centralised country: we have fewer democratically elected politicians per head of population than most other developed democracies in the world. Our concern with these measures is that they further reduce the voice of a local resident through their democratic representative about a decision that may be the most significant thing affecting their home or their neighbourhood in their entire life.

By creating a national scheme of delegations, we go beyond a point of saying that all local authorities must ensure, in the delivery of a quasi-judicial process, that they are following the law. We begin to say that this is no longer a delegation: it is compulsory. We are taking away the democratic power of the local authority, under which it delegates those decisions to planning committees and to officers, and we are deciding in Whitehall who will make those decisions.

While I absolutely respect what the Minister is saying about expert planning officers, having served in the last Parliament as the chair of the all-party parliamentary group on housing and planning and worked very closely with the RTPI, I think we need to be realistic. In many cases, when the Minister says “expert planning officers”, we are talking about newly minted graduates who do not live in—and have no experience of—the local area. They arrive and undertake a desk-based exercise to make these decisions. They are not highly experienced people with a level of local insight who understand why particular aspects of design, materials, or the nature of a development will have a real impact on a neighbourhood.

There are specific examples; one is applications by elected members themselves. I know from my time as a councillor in Hillingdon that a standard rule to ensure transparency is that any application by an elected councillor must be heard by a committee. If someone wishes to change the windows in their home, or build a loft extension, it has to go through a planning committee, even when those things are covered by permitted development rights. That was to ensure that level of transparency. It is not clear how such issues are dealt with through this proposed scheme of delegation.

Matters of detail can be critical: ensuring the acceptance of a proposed development at a neighbourhood level may often come down to issues like overlooking or how it respects the privacy of neighbours. Does it have tree planting, to screen developments that people are unhappy to see? Will there be mitigations around noise? Those are not trivial matters; they have a huge impact on people’s quality of life. The ability of elected representatives to say, “This decision made, entirely in accordance with planning law, needs to be taken transparently in public so that these representations can be heard” is critical.

--- Later in debate ---
--- Later in debate ---
Matthew Pennycook Portrait Matthew Pennycook
- Hansard - - - Excerpts

I thank the hon. Gentleman for reminding me of that point. It is a point well made, and it was also made by the shadow Minister on another clause. I will go away and reflect on what more, if anything, needs to be done in that regard. It is rightly put that, just as we want to ensure consistency in decisions by elected Members, we want consistency in the decisions and recommendations made by expert planning officers at a local authority level. I will happily come back to the Committee on that.

David Simmonds Portrait David Simmonds
- Hansard - -

I gently say to the Minister, who I look up to in many ways, that it is a challenge for the Committee to rely upon, on the one hand, an argument that this is not a big deal because it would affect hardly any planning applications, and on the other hand, an argument that it is so important we have to push it through via a national scheme of delegation. The concern that Members have is considering the 4% of applications that go to committee as a major problem, when in fact, by general acceptance in today’s debate, they are not really much of an issue. We lose the important element of local democratic accountability without any corresponding benefit in planning delivery.

Matthew Pennycook Portrait Matthew Pennycook
- Hansard - - - Excerpts

I would say two things to the hon. Gentleman. First, we do think there is a corresponding benefit, because we think the change will remove a large element of risk and uncertainty in the system and ensure some very important applications are made in a more timely way. I end by inviting the shadow Minister, at the point we publish our proposals, to come back on whether we have got the balance right. I am more than happy to continue the conversation about what we take forward on the regulations. On the principle of introducing a national scheme of delegation, the Government feel very strongly that it is the right thing to do.

Question put, That the amendment be made.