Govia Thameslink Franchise

Daniel Zeichner Excerpts
Wednesday 18th July 2018

(6 years, 5 months ago)

Commons Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts

Urgent Questions are proposed each morning by backbench MPs, and up to two may be selected each day by the Speaker. Chosen Urgent Questions are announced 30 minutes before Parliament sits each day.

Each Urgent Question requires a Government Minister to give a response on the debate topic.

This information is provided by Parallel Parliament and does not comprise part of the offical record

Daniel Zeichner Portrait Daniel Zeichner (Cambridge) (Lab)
- Hansard - -

“Not functioning properly” is a woeful understatement of the continuing misery that passengers from Cambridge are enduring. It started with the cancellation of peak-time services on Monday morning, when people who wanted to go to Kings Cross were told that they would be better off going to Liverpool Street. The previous evening I read in the Cambridge News that people who went to see Paul Simon found themselves left in London and had to pay £150 for a cab home. GTR will forever be remembered as the great train robbery. Has the Minister got a target for GTR to meet by next week? If it does not meet the target, will he finally strip it of the franchise?

Lord Johnson of Marylebone Portrait Joseph Johnson
- Hansard - - - Excerpts

The hard review, which we have discussed this afternoon, is under way. It got going on 21 June, and it is looking carefully at the performance of the new timetable. This is early days—we are on day four of the new timetable—and it is important that we give it a bit of time to bed in before we leap to conclusions. We want to make sure that we get the processes right. Performance yesterday was significantly better than it had been prior to the introduction of the interim timetable, with public performance measures in the 80s. The PPM for Great Northern, which I believe is relevant to the hon. Gentleman’s constituency, was 86%. Some issues this morning with Network Rail performance have affected services out of Cambridge, but they are not GTR’s responsibility.